Skip to Content

A window on interpreting insurance contracts: Top 10 points from Ledcor Construction

Jennifer Taylor

Introduction

Thanks to some dirty windows, insurance lawyers have a new go-to Supreme Court case on issues of policy interpretation: Ledcor Construction Ltd v Northbridge Indemnity Insurance Co2016 SCC 37.

The insurers in Ledcor Construction had denied coverage for the cost of replacing windows on a building under construction, after the contractor hired to clean the windows ended up scratching and damaging them.

The particular interpretation issue arose from the (terribly worded) exclusion clause in the standard form builders’ risk policy that “denies coverage for the ‘cost of making good faulty workmanship’ but, as an exception to that exclusion, nonetheless covers ‘physical damage’ that ‘results’ from the faulty workmanship.1

According to Justice Wagner for the majority, the cost of re-cleaning the windows was excluded from coverage, but the cost of replacing the windows was covered.2 The replacement cost was estimated to be $2.5 million3 so the interpretive issue was not just a matter of pocket change.

This post takes a broader look at Ledcor Construction, and highlights the top 10 points for interpreting insurance contracts more generally (the first 3 relate to standard of review, because the Supreme Court can’t seem to get enough of that topic).

Standard of review

  1. The standard of review of correctness applies to the interpretation of standard form insurance contracts. The Supreme Court hinted at this in Sattva,4 but confirmed it in Ledcor Construction.5 A rule of thumb for characterizing the interpretation question, and thus determining the applicable standard of review on appeal, is whether the decision on interpretation is likely to have precedential value beyond the particular parties to the dispute.6 If so, consistency in interpretation is more important, and the interpretation question should be reviewed for correctness.7 If, instead, the interpretation won’t have much “impact beyond the parties” then it likely doesn’t have to be reviewed on that stricter standard, and the trial judge should be given more deference.8
  2. The “factual matrix” is a not a Keanu Reeves movie – it’s a key part of determining the applicable standard of review. According to the majority, if there is a “meaningful factual matrix that is specific to the parties to assist the interpretation process” then the interpretation question is probably one of mixed fact and law, “subject to deferential review on appeal.”9

    There was actually a (sort of philosophical?) dispute between the majority and Justice Cromwell, concurring, about whether all contracts have a factual matrix – aka a broader context for the court to consider – or not. So expect future litigation over the exact content and role of the “matrix.”10

  3. When in doubt about standard of review in contract interpretation cases, apply the “take it or leave it” test. Did the parties (or their lawyers) negotiate and draft the contract themselves, or was the contract “offered on a ‘take it or leave it’ basis”?11  The answer to the “take it or leave it” question will be “yes” for many, if not most, insurance contracts. Insurers send the applicable policy to the prospective insured, and the insured can purchase coverage or not. There’s no real room to negotiate the terms of the contract.12 This indicates it’s a standard form contract that should be reviewed for correctness, because the interpretation will have precedential value.

    Policy interpretation

  4. The analytical approach from Progressive Homes still applies.13The court must first determine whether there’s coverage (burden on insured); move on to examine any applicable exclusion clause(s) that could oust coverage (burden shifts to insurer); and, finally, determine whether there’s an applicable exception to the exclusion (burden shifts back to insured). We also know from Progressive Homes “that coverage provisions in insurance policies are interpreted broadly, and exclusion clauses narrowly.”
  5. If the language of the clause is clear and unambiguous, the court should give effect to it.15 This point falls into the “easier said than done” category, as lawyers are experts at pointing out alleged ambiguities in language (hence the varied jurisprudence on the faulty workmanship exclusion at issue in Ledcor Construction, and even the interpretive differences between Justice Wagner and Justice Cromwell).
  6. If the language is found to be ambiguous, then other “rules of contract construction” can come into play “to resolve that ambiguity.”16 Three such rules were reviewed, and are listed below as items 7-9.
  7. The parties’ reasonable expectations can be considered to resolve an ambiguity.17 If it’s a contract that the parties negotiated and drafted themselves, then the context may reveal their expectations.18 To be “reasonable,” their expected interpretation must be “supported by the language of the policy” (which is a bit circular because, if this rule is being applied, it’s already been determined that the language is ambiguous…).

    If it’s a standard form contract, however, the court will take a broader, more purposive approach, to consider the “purpose behind” the type of policy and the particular coverage at issue, and to determine what the parties must have expected.19 If the insurer’s suggested interpretation would effectively gut or void the coverage that the insured thought they were purchasing, then the insured is more likely to succeed (at least when this interpretive rule is applied).20

  8. “Commercial reality” can also be considered to resolve an ambiguity.21 Unfortunately, this term is not defined. But essentially, an interpretation consistent with commercial reality will mean that neither party receives a windfall as a result. As Justice Estey stated in the classic case of Consolidated-Bathurst: “…the courts should be loath to support a construction which would either enable the insurer to pocket the premium without risk or the insured to achieve a recovery which could neither be sensibly sought nor anticipated at the time of the contract.”22
  9. A court interpreting an ambiguous clause should adopt the interpretation most consistent with the case law.23 This seems like a basic point of stare decisis, but it was emphasized in Ledcor Construction (even though the Supreme Court didn’t have to follow the lower courts…and even though the majority and concurring reasons disagreed on what the prior cases even said).
  10. The contra proferentem rule only applies if these rules of construction fail to untangle the ambiguity.24 The court will not arrive automatically at the interpretation that favours the insured, but must jump through several hoops first. (Or maybe that’s just the cynical view, through the windows of Ledcor Construction.)

1 Para 1.
2 Paras 5, 95.
3 Para 8.
4 Sattva Capital Corp v Creston Moly Corp2014 SCC 53.
5 Paras 4, 19-32.
6 Para 39.
7 Paras 40-42.
8 Para 37.
9 Para 24, 27, 30-32. See also paras 46, 48.
10 See e.g. para 116, Cromwell J, concurring.
11 Paras 20, 25, 28.
12 Para 29.
13 Para 52, citing Progressive Homes Ltd v Lombard General Insurance Co of Canada2010 SCC 33.
14 Para 51, citing Progressive Homes.
15 Para 49.
16 Para 50.
17 Para 50.
18 Although note Justice Wagner’s reluctance (at para 74, as part of the “reasonable expectations” discussion) to consider the service contract between the project owner and the window cleaning contractor as relevant to interpreting the exclusion clause.
19 Paras 65-66.
20 Paras 67-70.
21 Para 78.
22 Para 79, citing Consolidated Bathurst Export Ltd v Mutual Boiler and Machinery Insurance Co, [1980] 1 S.C.R. 888, 1979 CanLII 10 (SCC).
23 Para 84.
24 Paras 51, 96.

Archive

Dealing with Canadian “retaliatory” tariffs: A primer for importers

BY Michelle Chai & Graeme Hiebert

By Michelle Chai & Graeme Hiebert In response to the 25% tariffs levied on virtually all Canadian goods by the United States, Canada has announced United States Surtax Order (2025-1)…

Read More

Balancing inclusivity and workplace safety

BY Sheila Mecking & Lauren Sorel

By Sheila Mecking and Lauren Sorel Introduction Arbitrator Trisha Perry addressed the complex interests between inclusive education and workplace safety in a recent decision (New Brunswick Teachers’ Federation v New…

Read More

University governance in Nova Scotia: The impacts of Bill 12

BY Colleen Keyes,
K.C.
& Harper Metler

By Colleen Keyes, K.C. and Harper Metler On February 19, 2025, the Nova Scotia Government introduced Bill No. 12: An Act Respecting Advanced Education and Research (“Bill 12”), which is…

Read More

Privacy rights in the workplace: Supreme Court expands charter protections for public school teachers

BY Chad Sullivan & Chiara Nannucci

By Chad Sullivan and Chiara Nannucci Introduction A recent Supreme Court of Canada decision (York Region District School Board v. Elementary Teachers’ Federation of Ontario, 2024 SCC 22) has once…

Read More

New rules allowing Nova Scotia private sector employers to join Public Service Superannuation Plan take effect

BY Dante Manna & Noah Archibald

By Dante Manna and Noah Archibald The Provincial Government recently proclaimed the Private Sector Pension Plan Transfer Act (the “Transfer Act”) and newly released regulations on February 4, 2025. The…

Read More

Outlook for 2025 proxy season

By Andrew V. Burke, Colleen P. Keyes, Gavin Stuttard, David F. Slipp and Logan G. Walters With proxy season on the horizon, many public companies are once again preparing their…

Read More

Here we go again … how recent updates to Canada’s supply chain transparency reporting guidance may impact your 2025 reporting obligations

By Christine Pound, Colleen Keyes, K.C., and Daniel Roth As reporting entities and government institutions prepare their supply chain transparency reports, Public Safety Canada (“PSC“) has updated its guidance for…

Read More

Energy Watch 2025

Stewart McKelvey is pleased to present Energy Watch – a review of key legislative and policy advancements in the renewable energy sector in 2024 in Newfoundland and Labrador, Nova Scotia and New Brunswick and a look forward to anticipated activities in 2025.

Read More

Land use planning in Prince Edward Island – the year in review

BY Curtis Doyle

By Curtis Doyle Once again, the time has come to review the year that was and to chart the course for the year ahead. For municipalities and planning professionals in…

Read More

The impact of possible tariff changes on Canadian importers and strategies for consideration (Part II)

BY Michelle Chai & Graeme Hiebert

By Michelle Chai and Graeme Hiebert This is the second in a two-part Thought Leadership series. To read Part I, click here. Appearance, design, best use, marketing and distribution While the…

Read More

Search Archive