The Winds of Change (Part 7): Paying the Piper: New Newfoundland and Labrador Fiscal Framework expects billions in revenues from wind to hydrogen projects
By Dave Randell, G. John Samms, and Stuart Wallace
With the deadline for bids on crown lands available for wind energy projects extended to noon on March 23rd, the latest development in our Winds of Change series looks at the recently announced fiscal framework of Wind-Hydrogen projects in Newfoundland & Labrador
On February 23, 2023, the Newfoundland and Labrador Department of Industry, Energy and Technology announced further information on the fiscal framework of Wind-Hydrogen projects. This article sets out to provide a basic outline the specifics of the framework.
Principles
Predictability and transparency are the intended principles on which the fiscal framework has been developed. This is intended allow investors to make informed decisions. The framework attempts to balance the risk of investment with the use of provincial resources.
Payment Components
For a singular project over a 30-year period, the government of Newfoundland and Labrador expects $3.5B in taxes, royalties and fees.[1]
Payments will occur early in the project, and throughout the operation phase. These payments can be broken into three components: Land, Wind, and Water.
Land
- Crown Land Reserve Fee: Annual charge of 3.5% of the market value of reserved lands. Payments begin upon award of exclusive right to pursue projects on lands.
- Crown Land Lease Fee: Annual charge of 7% of market value of land. Payments begin upon issuance of Crown Land lease.
Wind
- Wind Electricity Tax: Annual charge of $4,000 per megawatt on installed capacity. Payments begin when the turbines are “in-service”, and applicable to all wind-hydrogen projects (≥ 5 megawatts) producing electricity for the purposes of producing hydrogen.
Water
- Water Use Fee: Annual charge of $500 per 1000m3 of water licensed and used, and $50 per 1000m3 of water licensed but not used. Payments begin when permit is issued, and are applicable to all hydrogen facilities.
- Water Royalty: Payable based on the calculated residual value of the water. Rates are tiered and linked to cost recovery. These terms can be modified via agreements with the Province. Further details about calculation in document.
- Tier 1: Rate of 10% applied after 1x cost recovery.
- Tier 2: Rate of 20% applied after 2x cost recovery.
- Tier 3: Rate of 25% applied after 3x cost recovery.
Taxes
Taxes will be applicable to all wind projects producing electricity for the purposes of producing hydrogen. For more information on how Atlantic Canada is poised to benefit from clean energy tax credits, check out part 5 of this series.
Bids
Deadline for submitting bids has been extended to March 23, 2023.
Successful Bidders will be awarded the exclusive right to pursue their project through the Crown Lands and Environmental Assessment processes.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership.
[1] Using a base case of a 1000 MW Windfarm and a 500 MW Hydrogen (Ammonia) Facility with capital costs of $3.5 billion with an annual production of 60k tonnes of hydrogen converted to 344k tonnes of ammonia.
Archive
The New Brunswick government is seeking feedback from stakeholders on proposed changes to the Employment Standards Act (“Act”). The proposed changes relate to: – the statutory minimum wage; – employment protections for young workers; and – coverage…
Read MoreOCTOBER 19, 2015 – FEDERAL ELECTION A Federal election has been called for Monday, October 19, 2015. Polls are open in Atlantic Canada from 8:30 a.m. to 8:30 p.m. Advance polls are open from…
Read MoreAs of August 1, 2015, section 4 of the Nova Scotia Automobile Tort Recovery Limitations Regulations was repealed. This section previously set the discount rate for future losses in automobile tort claims at 3.5%. The repeal…
Read MoreOn September 9, 2015, the Nova Scotia Department of Finance and Treasury Board opened a consultation on draft Regulations for Pooled Registered Pension Plans (PRPPs). The draft Regulations and an FAQ are posted online. PRPPs are…
Read MoreBy Jennifer Taylor – Research Lawyer September used to mean one thing: back to school. This year, Nova Scotia lawyers get a fresh learning opportunity of a different sort. It comes in the form of the new Limitation…
Read MoreTHE EDITORS’ CORNER Michelle Black and Sean Kelly Aaah, summer – that long anticipated stretch of lazy, lingering days, free of responsibility and rife with possibility. It’s a time to hunt for insects, master handstands, practice swimming…
Read MoreThe New Public Contracting World As part of an ongoing initiative aimed at ensuring Canada only does business with ethical suppliers, Public Works and Government Services Canada (“PWGSC”) has introduced changes to its Integrity Regime…
Read MoreIn an important case for insurance practice in Nova Scotia, the Court of Appeal has confirmed that the value of future CPP disability benefits is deductible under the SEF 44 family protection endorsement. Justice Scanlan wrote the…
Read MoreIn order to streamline the continuous disclosure obligations of venture issuers, the Canadian Securities Administrators (“CSA”) are implementing amendments to the national instruments and companion policies listed below, that will come into force across Canada…
Read MoreOn April 21, 2015, the Nova Scotia government declared that the new Pension Benefits Act (passed in 2011) and new Pension Benefits Regulations will come into effect on June 1, 2015. The new Regulations follow the new Act and draft Regulations summarized in…
Read More