The Winds of Change (Part 7): Paying the Piper: New Newfoundland and Labrador Fiscal Framework expects billions in revenues from wind to hydrogen projects
By Dave Randell, G. John Samms, and Stuart Wallace
With the deadline for bids on crown lands available for wind energy projects extended to noon on March 23rd, the latest development in our Winds of Change series looks at the recently announced fiscal framework of Wind-Hydrogen projects in Newfoundland & Labrador
On February 23, 2023, the Newfoundland and Labrador Department of Industry, Energy and Technology announced further information on the fiscal framework of Wind-Hydrogen projects. This article sets out to provide a basic outline the specifics of the framework.
Principles
Predictability and transparency are the intended principles on which the fiscal framework has been developed. This is intended allow investors to make informed decisions. The framework attempts to balance the risk of investment with the use of provincial resources.
Payment Components
For a singular project over a 30-year period, the government of Newfoundland and Labrador expects $3.5B in taxes, royalties and fees.[1]
Payments will occur early in the project, and throughout the operation phase. These payments can be broken into three components: Land, Wind, and Water.
Land
- Crown Land Reserve Fee: Annual charge of 3.5% of the market value of reserved lands. Payments begin upon award of exclusive right to pursue projects on lands.
- Crown Land Lease Fee: Annual charge of 7% of market value of land. Payments begin upon issuance of Crown Land lease.
Wind
- Wind Electricity Tax: Annual charge of $4,000 per megawatt on installed capacity. Payments begin when the turbines are “in-service”, and applicable to all wind-hydrogen projects (≥ 5 megawatts) producing electricity for the purposes of producing hydrogen.
Water
- Water Use Fee: Annual charge of $500 per 1000m3 of water licensed and used, and $50 per 1000m3 of water licensed but not used. Payments begin when permit is issued, and are applicable to all hydrogen facilities.
- Water Royalty: Payable based on the calculated residual value of the water. Rates are tiered and linked to cost recovery. These terms can be modified via agreements with the Province. Further details about calculation in document.
- Tier 1: Rate of 10% applied after 1x cost recovery.
- Tier 2: Rate of 20% applied after 2x cost recovery.
- Tier 3: Rate of 25% applied after 3x cost recovery.
Taxes
Taxes will be applicable to all wind projects producing electricity for the purposes of producing hydrogen. For more information on how Atlantic Canada is poised to benefit from clean energy tax credits, check out part 5 of this series.
Bids
Deadline for submitting bids has been extended to March 23, 2023.
Successful Bidders will be awarded the exclusive right to pursue their project through the Crown Lands and Environmental Assessment processes.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership.
[1] Using a base case of a 1000 MW Windfarm and a 500 MW Hydrogen (Ammonia) Facility with capital costs of $3.5 billion with an annual production of 60k tonnes of hydrogen converted to 344k tonnes of ammonia.
Archive
Rob Aske You likely heard rumblings over the spring and summer, but now it’s here. Canada’s federal privacy law known by the acronym PIPEDA (Personal Information Protection and Electronic Documents Act) adds privacy breach reporting…
Read MoreGuy-Etienne Richard The Nova Scotia government introduced Bill 29 on September 14, 2018 to increase pregnancy and parental leave to reflect the recent changes by the federal government to Employment Insurance (“EI”). Those EI changes…
Read MoreWe are pleased to present the third issue of Discovery: Atlantic Education and the Law, our very own legal publication targeted to educational institutions in Atlantic Canada. A new school year has begun and fall…
Read MoreKevin Landry News articles have reported Canadians being labelled as “inadmissible” or being denied entry at the United States’ border because of ties to the cannabis industry. Being labeled inadmissible by border authorities is the…
Read MoreJonathan Coady and Justin Milne On June 25, 2018, the Supreme Court of Prince Edward Island (the “Supreme Court”) released its much anticipated decision in Mi’kmaq of P.E.I. v. Province of P.E.I.2 This is the first…
Read MoreKevin Landry Health Canada released the Cannabis Act Regulations (the “Regulations”) at a news conference on June 27, 2018. The Regulations will be published in final form in the July 11, 2018 version of in…
Read MoreAndrew Burke, David Randell and Divya Subramanian There is never a dull moment when it comes to cryptocurrency: whether it is the hacking of a South Korean crypto exchange, the U.S. Securities and Exchange Commission…
Read MoreGrant Machum and Sheila Mecking While most people think Canada Day is on July 1st, once every 6 years, July 1st falls on a Sunday. When that happens, according to federal legislation, Canada Day is…
Read MoreJames Travers, QC and Justin Milne A new Bill, the Business Corporations Act (“Act”), recently passed by the Prince Edward Island legislature, has made significant changes to the way corporations will be governed in Prince…
Read MorePerlene Morrison and Hilary Newman Municipalities in Prince Edward Island entered a new era when the Municipal Government Act (the “MGA”) was proclaimed into force on December 23, 2017. The MGA modernized the Province’s municipal…
Read More