The Winds of Change (Part 7): Paying the Piper: New Newfoundland and Labrador Fiscal Framework expects billions in revenues from wind to hydrogen projects
By Dave Randell, G. John Samms, and Stuart Wallace
With the deadline for bids on crown lands available for wind energy projects extended to noon on March 23rd, the latest development in our Winds of Change series looks at the recently announced fiscal framework of Wind-Hydrogen projects in Newfoundland & Labrador
On February 23, 2023, the Newfoundland and Labrador Department of Industry, Energy and Technology announced further information on the fiscal framework of Wind-Hydrogen projects. This article sets out to provide a basic outline the specifics of the framework.
Principles
Predictability and transparency are the intended principles on which the fiscal framework has been developed. This is intended allow investors to make informed decisions. The framework attempts to balance the risk of investment with the use of provincial resources.
Payment Components
For a singular project over a 30-year period, the government of Newfoundland and Labrador expects $3.5B in taxes, royalties and fees.[1]
Payments will occur early in the project, and throughout the operation phase. These payments can be broken into three components: Land, Wind, and Water.
Land
- Crown Land Reserve Fee: Annual charge of 3.5% of the market value of reserved lands. Payments begin upon award of exclusive right to pursue projects on lands.
- Crown Land Lease Fee: Annual charge of 7% of market value of land. Payments begin upon issuance of Crown Land lease.
Wind
- Wind Electricity Tax: Annual charge of $4,000 per megawatt on installed capacity. Payments begin when the turbines are “in-service”, and applicable to all wind-hydrogen projects (≥ 5 megawatts) producing electricity for the purposes of producing hydrogen.
Water
- Water Use Fee: Annual charge of $500 per 1000m3 of water licensed and used, and $50 per 1000m3 of water licensed but not used. Payments begin when permit is issued, and are applicable to all hydrogen facilities.
- Water Royalty: Payable based on the calculated residual value of the water. Rates are tiered and linked to cost recovery. These terms can be modified via agreements with the Province. Further details about calculation in document.
- Tier 1: Rate of 10% applied after 1x cost recovery.
- Tier 2: Rate of 20% applied after 2x cost recovery.
- Tier 3: Rate of 25% applied after 3x cost recovery.
Taxes
Taxes will be applicable to all wind projects producing electricity for the purposes of producing hydrogen. For more information on how Atlantic Canada is poised to benefit from clean energy tax credits, check out part 5 of this series.
Bids
Deadline for submitting bids has been extended to March 23, 2023.
Successful Bidders will be awarded the exclusive right to pursue their project through the Crown Lands and Environmental Assessment processes.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership.
[1] Using a base case of a 1000 MW Windfarm and a 500 MW Hydrogen (Ammonia) Facility with capital costs of $3.5 billion with an annual production of 60k tonnes of hydrogen converted to 344k tonnes of ammonia.
Archive
EDITOR’S COMMENT This edition of Atlantic Employers’ Counsel focuses on key areas of employment standards in Atlantic Canada. Employment standards legislation outlines the rights and obligations of employees and requirements that apply to employers in…
Read MoreNEW TORT OF CYBERBULLYING On May 10, 2013 the Nova Scotia legislature passed the Cyber-safety Act (Bill 61). When this bill comes into force, it will give rise to a new tort of cyberbullying that…
Read MoreGOVERNMENT ACTION In the Economic Action Plan 2010, the Harper Government committed to bring greater clarity to how mortgage prepayment penalties were calculated. As part of the commitment, on February 26, 2013 the government released…
Read MoreSTEWART MCKELVEY WELCOMES BACK WANDA DOIRON AS MANAGER, CORPORATE SERVICES – NOVA SCOTIA You might remember Wanda from her time in our Corporate Services group from 2002 to 2008. Since then, she has worked in-house…
Read MoreREASONABLE PEOPLE DOING QUESTIONABLE THINGS: CONFLICTS OF INTEREST AND JUST CAUSE Can a unionized employee moonlight in his off hours to earn some extra money by doing the same work he does for his daytime…
Read MoreStewart McKelvey’s Vision Improving Legal Analysis (SVILA*) is an e-discovery project and litigation management tool. For more information on our e-discovery services, download the SVILA e-discovery document.
Read MoreIN THIS ISSUE: A New Brunswick business lawyer’s perspective by Peter Klohn Why Canada’s immigration rules matter to your business by Andrea Baldwin Financing Energy Projects during the Project Lifecycle by Lydia Bugden, Colm St. Roch Seviour and Tauna Staniland Download…
Read MoreYellow diamonds in the light And we’re standing side by side As your shadow crosses mine What it takes to come alive It’s the way I’m feeling I just can’t deny But I’ve gotta let…
Read MoreINTRODUCTION On December 6, 2012, The Nova Scotia Department of Environment (NSE) released Draft Ministerial Protocols (the “Draft Protocols”) related to contaminated sites. The release of the Draft Protocols has been eagerly anticipated. The adoption…
Read MoreRecent changes to the Rules of the Supreme Court, 1986, SNL 1986, c 42, Sch D On December 14, 2012, several changes were made to the Rules of the Supreme Court. These changes include: who may act…
Read More