The Winds of Change (Part 7): Paying the Piper: New Newfoundland and Labrador Fiscal Framework expects billions in revenues from wind to hydrogen projects
By Dave Randell, G. John Samms, and Stuart Wallace
With the deadline for bids on crown lands available for wind energy projects extended to noon on March 23rd, the latest development in our Winds of Change series looks at the recently announced fiscal framework of Wind-Hydrogen projects in Newfoundland & Labrador
On February 23, 2023, the Newfoundland and Labrador Department of Industry, Energy and Technology announced further information on the fiscal framework of Wind-Hydrogen projects. This article sets out to provide a basic outline the specifics of the framework.
Principles
Predictability and transparency are the intended principles on which the fiscal framework has been developed. This is intended allow investors to make informed decisions. The framework attempts to balance the risk of investment with the use of provincial resources.
Payment Components
For a singular project over a 30-year period, the government of Newfoundland and Labrador expects $3.5B in taxes, royalties and fees.[1]
Payments will occur early in the project, and throughout the operation phase. These payments can be broken into three components: Land, Wind, and Water.
Land
- Crown Land Reserve Fee: Annual charge of 3.5% of the market value of reserved lands. Payments begin upon award of exclusive right to pursue projects on lands.
- Crown Land Lease Fee: Annual charge of 7% of market value of land. Payments begin upon issuance of Crown Land lease.
Wind
- Wind Electricity Tax: Annual charge of $4,000 per megawatt on installed capacity. Payments begin when the turbines are “in-service”, and applicable to all wind-hydrogen projects (≥ 5 megawatts) producing electricity for the purposes of producing hydrogen.
Water
- Water Use Fee: Annual charge of $500 per 1000m3 of water licensed and used, and $50 per 1000m3 of water licensed but not used. Payments begin when permit is issued, and are applicable to all hydrogen facilities.
- Water Royalty: Payable based on the calculated residual value of the water. Rates are tiered and linked to cost recovery. These terms can be modified via agreements with the Province. Further details about calculation in document.
- Tier 1: Rate of 10% applied after 1x cost recovery.
- Tier 2: Rate of 20% applied after 2x cost recovery.
- Tier 3: Rate of 25% applied after 3x cost recovery.
Taxes
Taxes will be applicable to all wind projects producing electricity for the purposes of producing hydrogen. For more information on how Atlantic Canada is poised to benefit from clean energy tax credits, check out part 5 of this series.
Bids
Deadline for submitting bids has been extended to March 23, 2023.
Successful Bidders will be awarded the exclusive right to pursue their project through the Crown Lands and Environmental Assessment processes.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership.
[1] Using a base case of a 1000 MW Windfarm and a 500 MW Hydrogen (Ammonia) Facility with capital costs of $3.5 billion with an annual production of 60k tonnes of hydrogen converted to 344k tonnes of ammonia.
Archive
We previously circulated a client update regarding contemplated changes to automobile insurance in Prince Edward Island. Government has now published a consultation paper (www.gov.pe.ca/photos/original/eljautoinreform.pdf), seeking responses in writing on or before December 2, 2013. According to the consultation…
Read MoreThe Association of Caribbean Corporate Counsel (ACCC) released the inaugural edition of its quarterly journal, Caribbean Corporate Counsel, featuring CEO, John Rogers, Q.C., advisor on the International Advisory Board, and an article by partner Paul Smith, entitled “Governance…
Read MoreCHANGES, CHANGES AND MORE CHANGES: KEEPING UP WITH THE TEMPORARY FOREIGN WORKER PROGRAM These days, Canada’s Temporary Foreign Worker Program (“TFWP”) is more top of mind than ever for Canadian employers. This is in part…
Read MoreBy October 17, 2014 existing not-for-profit corporations incorporated under Part II of the Canada Corporations Act (the “Old Act”) are required to be continued under the new Canada Not-for-Profit Corporations Act (the “New Act”) or face the possibility of automatic administrative…
Read MoreIN THIS ISSUE: Reasonable Cause: A necessary prerequisite for random alcohol testing policies by Mark Tector, Steve Carpenter, CHRP, Melissa Everett Withers, Ruth Trask Business Succession: Why is it critical? by Richard Niedermayer, TEP Privacy Please: Nova Scotia brings in new…
Read MoreOn May 19, 2011, Nova Scotia’s Labour Standards Code was amended to protect foreign workers from exploitation by recruiters and employers. These amendments imposed a requirement for third-party recruiters to obtain a license from the Province to…
Read MoreFacts This appeal arose from a decision which held that the Dominion of Canada General Insurance Company (“Dominion”) has a duty to defend Larry and Lona Hannam and their teenage son Jordan in an action…
Read MoreDUE DILIGENCE Generally, occupational health and safety legislation in Atlantic Canada, like other jurisdictions, requires employers to take reasonable precautions to ensure the health and safety of workers in their workplace. Read More INCIDENT RESPONSE…
Read MoreThe Cyber-safety Act (“the Act”), excepting Part V (that part amending the Safer Communities and Neighbourhoods Act), was proclaimed August 6, 2013 and is now in effect. As discussed in our May 17, 2013 Client Update and our HRLaw blog The business case…
Read MoreThe Supreme Court of Canada has now released the much anticipated decision in the case of Marine Services International Ltd. v Ryan Estate, 2013 SCC 44. In doing so, the high court has signaled, at least…
Read More