The Winds of Change (Part 7): Paying the Piper: New Newfoundland and Labrador Fiscal Framework expects billions in revenues from wind to hydrogen projects
By Dave Randell, G. John Samms, and Stuart Wallace
With the deadline for bids on crown lands available for wind energy projects extended to noon on March 23rd, the latest development in our Winds of Change series looks at the recently announced fiscal framework of Wind-Hydrogen projects in Newfoundland & Labrador
On February 23, 2023, the Newfoundland and Labrador Department of Industry, Energy and Technology announced further information on the fiscal framework of Wind-Hydrogen projects. This article sets out to provide a basic outline the specifics of the framework.
Principles
Predictability and transparency are the intended principles on which the fiscal framework has been developed. This is intended allow investors to make informed decisions. The framework attempts to balance the risk of investment with the use of provincial resources.
Payment Components
For a singular project over a 30-year period, the government of Newfoundland and Labrador expects $3.5B in taxes, royalties and fees.[1]
Payments will occur early in the project, and throughout the operation phase. These payments can be broken into three components: Land, Wind, and Water.
Land
- Crown Land Reserve Fee: Annual charge of 3.5% of the market value of reserved lands. Payments begin upon award of exclusive right to pursue projects on lands.
- Crown Land Lease Fee: Annual charge of 7% of market value of land. Payments begin upon issuance of Crown Land lease.
Wind
- Wind Electricity Tax: Annual charge of $4,000 per megawatt on installed capacity. Payments begin when the turbines are “in-service”, and applicable to all wind-hydrogen projects (≥ 5 megawatts) producing electricity for the purposes of producing hydrogen.
Water
- Water Use Fee: Annual charge of $500 per 1000m3 of water licensed and used, and $50 per 1000m3 of water licensed but not used. Payments begin when permit is issued, and are applicable to all hydrogen facilities.
- Water Royalty: Payable based on the calculated residual value of the water. Rates are tiered and linked to cost recovery. These terms can be modified via agreements with the Province. Further details about calculation in document.
- Tier 1: Rate of 10% applied after 1x cost recovery.
- Tier 2: Rate of 20% applied after 2x cost recovery.
- Tier 3: Rate of 25% applied after 3x cost recovery.
Taxes
Taxes will be applicable to all wind projects producing electricity for the purposes of producing hydrogen. For more information on how Atlantic Canada is poised to benefit from clean energy tax credits, check out part 5 of this series.
Bids
Deadline for submitting bids has been extended to March 23, 2023.
Successful Bidders will be awarded the exclusive right to pursue their project through the Crown Lands and Environmental Assessment processes.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership.
[1] Using a base case of a 1000 MW Windfarm and a 500 MW Hydrogen (Ammonia) Facility with capital costs of $3.5 billion with an annual production of 60k tonnes of hydrogen converted to 344k tonnes of ammonia.
Archive
The Island Regulatory and Appeals Commission (the “Commission”) has issued a holiday reminder to municipalities in Prince Edward Island about the importance of preparation, accuracy, and transparency when making decisions related to land use and…
Read MoreBy Brian G. Johnston, QC On the same day that the Nova Scotia government announced its projected deficit had ballooned to $241 million, it also introduced Bill 148, the Public Services Sustainability (2015) Act (“Act”). The stated purposes…
Read MoreBy Jennifer Taylor – Research Lawyer Nova Scotia’s Cyber-safety Act1 is no more, after a successful Charterchallenge to the legislation. In Crouch v Snell, 2015 NSSC 340, Justice McDougall of the Supreme Court of Nova Scotia found the entire statute—enacted in…
Read MoreBy Jennifer Taylor Introduction: Did Ontario have jurisdiction? Arguments about access to justice are not enough to oust the general principles of jurisdiction, according to a recent Ontario case. In Forsythe v Westfall, 2015 ONCA 810, the…
Read MorePART I: THE NSCA DECISION IN BRINE “Disability insurance is a peace of mind contract”: that’s the opening line of the Nova Scotia Court of Appeal’s long-awaited decision in Industrial Alliance Insurance and Financial Services Inc…
Read MoreThe taxation of estates, testamentary trusts and certain “life interest trusts” such as alter ego, joint partner and spousal trusts, and the rules for charitable donations made on death through an estate are changing significantly…
Read MoreSeveral important changes in the tax rules that apply to charitable gifts will be coming into effect in the near future. Some of the new rules take effect in 2016, and others will apply beginning…
Read MoreTHE EDITORS’ CORNER Michelle Black and Sean Kelly Trick, Treat or … Taunt? Workplace Bullying and Harassment Fall has arrived! The leaves are changing colours, families are stockpiling Halloween candy (some of which will actually last long…
Read MoreBy Jennifer Taylor – Research Lawyer With the federal election just days away, voting is on Canadians’ minds. This will be the first election conducted in accordance with the Fair Elections Act, SC 2014, c 12 [“FEA”] which…
Read MoreBy Jennifer Taylor Introduction There is now a Nova Scotia decision on the interplay between the provincial Builders’ Lien Act and the federal Bankruptcy and Insolvency Act (“BIA”) in the interesting context of trusts. In Re Kel-Greg Homes Inc, Justice Rosinski…
Read More