The Winds of Change (Part 7): Paying the Piper: New Newfoundland and Labrador Fiscal Framework expects billions in revenues from wind to hydrogen projects
By Dave Randell, G. John Samms, and Stuart Wallace
With the deadline for bids on crown lands available for wind energy projects extended to noon on March 23rd, the latest development in our Winds of Change series looks at the recently announced fiscal framework of Wind-Hydrogen projects in Newfoundland & Labrador
On February 23, 2023, the Newfoundland and Labrador Department of Industry, Energy and Technology announced further information on the fiscal framework of Wind-Hydrogen projects. This article sets out to provide a basic outline the specifics of the framework.
Principles
Predictability and transparency are the intended principles on which the fiscal framework has been developed. This is intended allow investors to make informed decisions. The framework attempts to balance the risk of investment with the use of provincial resources.
Payment Components
For a singular project over a 30-year period, the government of Newfoundland and Labrador expects $3.5B in taxes, royalties and fees.[1]
Payments will occur early in the project, and throughout the operation phase. These payments can be broken into three components: Land, Wind, and Water.
Land
- Crown Land Reserve Fee: Annual charge of 3.5% of the market value of reserved lands. Payments begin upon award of exclusive right to pursue projects on lands.
- Crown Land Lease Fee: Annual charge of 7% of market value of land. Payments begin upon issuance of Crown Land lease.
Wind
- Wind Electricity Tax: Annual charge of $4,000 per megawatt on installed capacity. Payments begin when the turbines are “in-service”, and applicable to all wind-hydrogen projects (≥ 5 megawatts) producing electricity for the purposes of producing hydrogen.
Water
- Water Use Fee: Annual charge of $500 per 1000m3 of water licensed and used, and $50 per 1000m3 of water licensed but not used. Payments begin when permit is issued, and are applicable to all hydrogen facilities.
- Water Royalty: Payable based on the calculated residual value of the water. Rates are tiered and linked to cost recovery. These terms can be modified via agreements with the Province. Further details about calculation in document.
- Tier 1: Rate of 10% applied after 1x cost recovery.
- Tier 2: Rate of 20% applied after 2x cost recovery.
- Tier 3: Rate of 25% applied after 3x cost recovery.
Taxes
Taxes will be applicable to all wind projects producing electricity for the purposes of producing hydrogen. For more information on how Atlantic Canada is poised to benefit from clean energy tax credits, check out part 5 of this series.
Bids
Deadline for submitting bids has been extended to March 23, 2023.
Successful Bidders will be awarded the exclusive right to pursue their project through the Crown Lands and Environmental Assessment processes.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership.
[1] Using a base case of a 1000 MW Windfarm and a 500 MW Hydrogen (Ammonia) Facility with capital costs of $3.5 billion with an annual production of 60k tonnes of hydrogen converted to 344k tonnes of ammonia.
Archive
By Jennifer Taylor Why is this case a big deal? It started with two salmon. Now, after several years of litigation, the Nova Scotia Provincial Court in R v Martin, 2016 NSPC 14 has stayed proceedings against…
Read MoreTHE EDITORS’ CORNER Michelle Black and Sean Kelly One day, the line between mental and physical disabilities may not be so pronounced, but, for now, distinctions are still drawn between Employee A with, for example, diabetes and…
Read MoreBy Lisa Gallivan Employees can be your biggest asset, if you hire the right people. This can often be one of the biggest decisions that you make as a business owner or employer. The “right” employee…
Read MoreBy Burtley Francis and Kathleen Leighton Order Up: Apple, P.I. Recently, the public safety versus personal privacy debate has been brought to main headlines. Apple is facing a court order (available here) requiring the company to assist the FBI in the investigation of…
Read MoreIn preparing for the 2016 proxy season, you should be aware of some regulatory changes and institutional investor guidance that may impact disclosure to and interactions with your shareholders. This update highlights what is new…
Read MoreBy Burtley Francis and Michael MacIsaac You remember Left Shark… The Super Bowl is a lot of things to a lot of people and is arguably the most anticipated event of the year that is not a holiday…
Read MoreBy Jennifer Taylor Summary The Canada Industrial Relations Board recently held that it had no jurisdiction as a federal board to certify a bargaining unit comprised of fisheries employees of the Waycobah First Nation. The decision…
Read MoreBy Peter McLellan, QC In the 1970s the issue for employers was long hair and sideburns. In the 1980’s it was earrings for men. Today the employer’s concerns are with tattoos and facial piercings. What are…
Read MoreBy Jennifer Taylor Introduction It sounds simple: Two disputing parties, hoping to resolve their disagreement without drawn-out court proceedings, will mutually agree to a settlement on clear terms; release each other from all claims; and move…
Read More2015 ends with changes in workplace laws that our region’s employers will want to be aware of moving into 2016. Some legislation has been proclaimed and is in force, some has passed and will be…
Read More