The Winds of Change (Part 7): Paying the Piper: New Newfoundland and Labrador Fiscal Framework expects billions in revenues from wind to hydrogen projects
By Dave Randell, G. John Samms, and Stuart Wallace
With the deadline for bids on crown lands available for wind energy projects extended to noon on March 23rd, the latest development in our Winds of Change series looks at the recently announced fiscal framework of Wind-Hydrogen projects in Newfoundland & Labrador
On February 23, 2023, the Newfoundland and Labrador Department of Industry, Energy and Technology announced further information on the fiscal framework of Wind-Hydrogen projects. This article sets out to provide a basic outline the specifics of the framework.
Principles
Predictability and transparency are the intended principles on which the fiscal framework has been developed. This is intended allow investors to make informed decisions. The framework attempts to balance the risk of investment with the use of provincial resources.
Payment Components
For a singular project over a 30-year period, the government of Newfoundland and Labrador expects $3.5B in taxes, royalties and fees.[1]
Payments will occur early in the project, and throughout the operation phase. These payments can be broken into three components: Land, Wind, and Water.
Land
- Crown Land Reserve Fee: Annual charge of 3.5% of the market value of reserved lands. Payments begin upon award of exclusive right to pursue projects on lands.
- Crown Land Lease Fee: Annual charge of 7% of market value of land. Payments begin upon issuance of Crown Land lease.
Wind
- Wind Electricity Tax: Annual charge of $4,000 per megawatt on installed capacity. Payments begin when the turbines are “in-service”, and applicable to all wind-hydrogen projects (≥ 5 megawatts) producing electricity for the purposes of producing hydrogen.
Water
- Water Use Fee: Annual charge of $500 per 1000m3 of water licensed and used, and $50 per 1000m3 of water licensed but not used. Payments begin when permit is issued, and are applicable to all hydrogen facilities.
- Water Royalty: Payable based on the calculated residual value of the water. Rates are tiered and linked to cost recovery. These terms can be modified via agreements with the Province. Further details about calculation in document.
- Tier 1: Rate of 10% applied after 1x cost recovery.
- Tier 2: Rate of 20% applied after 2x cost recovery.
- Tier 3: Rate of 25% applied after 3x cost recovery.
Taxes
Taxes will be applicable to all wind projects producing electricity for the purposes of producing hydrogen. For more information on how Atlantic Canada is poised to benefit from clean energy tax credits, check out part 5 of this series.
Bids
Deadline for submitting bids has been extended to March 23, 2023.
Successful Bidders will be awarded the exclusive right to pursue their project through the Crown Lands and Environmental Assessment processes.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership.
[1] Using a base case of a 1000 MW Windfarm and a 500 MW Hydrogen (Ammonia) Facility with capital costs of $3.5 billion with an annual production of 60k tonnes of hydrogen converted to 344k tonnes of ammonia.
Archive
Murray Murphy, QC, CPHR, and Charlotte Jenkins Mental health impacts of COVID-19 The mental health impacts of COVID-19 have been, and will continue to be significant and wide-spread around the world. Individuals are continuously required…
Read MoreNancy G. Rubin, QC and Erin McSorley In response to the immense public health and safety challenges posed by the COVID-19 pandemic, Courts across the country have modified their practices and procedures. This article provides…
Read MoreKathleen Leighton On March 18, 2020, Newfoundland and Labrador declared a public health emergency as a result of the COVID-19 pandemic. While a declaration of public health emergency is in effect, the Chief Medical Officer…
Read MoreBrian Johnston, QC and Brittany Trafford Governments and employers are strategizing ways to open economies, businesses and services following unprecedented closures around the world.1 In Canada, each Province is taking its own approach and various…
Read MoreStephanie Stapleford, Andrew Burke, Mike Carver, Matthew Craig and Divya Subramanian Part 1: Virtual shareholders’ meetings The escalating COVID-19 crisis, and federal, provincial and local governments’ directives for individuals to comply with social distancing policies,…
Read MoreKimberly Bungay In the spring sitting of the legislature, the Nova Scotia government introduced Bill 226, which amends the Companies Act (the “Act”) to require companies incorporated under the Act to create and maintain a…
Read MoreCatherine Lahey, QC, Iain Sinclair and Robert Bradley The Province of New Brunswick declared a State of Emergency on March 19, 2020 related to the COVID-19 pandemic and issued a Mandatory Order stipulating restrictions on…
Read MoreHalifax Partners Richard Niedermayer, TEP, Secretary, STEP Canada, and Tim Matthews, QC, TEP, and Articled Clerk Madeleine Coats, have prepared a useful resource for STEP Canada members outlining the options in place for having estate…
Read MoreJoe Thorne In our update on April 2, 2020, Newfoundland and Labrador passes law to allow variation periods and statutory timelines during COVID-19 pandemic, we reported on Newfoundland and Labrador’s passage of the Temporary Variation…
Read MoreRick Dunlop The question on many businesses’ mind is when and what exactly does an end to the COVID-19 lockdown look like. The Economist describes various European government’s easing of COVID-19 restrictions as being done…
Read More