The Winds of Change (Part 7): Paying the Piper: New Newfoundland and Labrador Fiscal Framework expects billions in revenues from wind to hydrogen projects
By Dave Randell, G. John Samms, and Stuart Wallace
With the deadline for bids on crown lands available for wind energy projects extended to noon on March 23rd, the latest development in our Winds of Change series looks at the recently announced fiscal framework of Wind-Hydrogen projects in Newfoundland & Labrador
On February 23, 2023, the Newfoundland and Labrador Department of Industry, Energy and Technology announced further information on the fiscal framework of Wind-Hydrogen projects. This article sets out to provide a basic outline the specifics of the framework.
Principles
Predictability and transparency are the intended principles on which the fiscal framework has been developed. This is intended allow investors to make informed decisions. The framework attempts to balance the risk of investment with the use of provincial resources.
Payment Components
For a singular project over a 30-year period, the government of Newfoundland and Labrador expects $3.5B in taxes, royalties and fees.[1]
Payments will occur early in the project, and throughout the operation phase. These payments can be broken into three components: Land, Wind, and Water.
Land
- Crown Land Reserve Fee: Annual charge of 3.5% of the market value of reserved lands. Payments begin upon award of exclusive right to pursue projects on lands.
- Crown Land Lease Fee: Annual charge of 7% of market value of land. Payments begin upon issuance of Crown Land lease.
Wind
- Wind Electricity Tax: Annual charge of $4,000 per megawatt on installed capacity. Payments begin when the turbines are “in-service”, and applicable to all wind-hydrogen projects (≥ 5 megawatts) producing electricity for the purposes of producing hydrogen.
Water
- Water Use Fee: Annual charge of $500 per 1000m3 of water licensed and used, and $50 per 1000m3 of water licensed but not used. Payments begin when permit is issued, and are applicable to all hydrogen facilities.
- Water Royalty: Payable based on the calculated residual value of the water. Rates are tiered and linked to cost recovery. These terms can be modified via agreements with the Province. Further details about calculation in document.
- Tier 1: Rate of 10% applied after 1x cost recovery.
- Tier 2: Rate of 20% applied after 2x cost recovery.
- Tier 3: Rate of 25% applied after 3x cost recovery.
Taxes
Taxes will be applicable to all wind projects producing electricity for the purposes of producing hydrogen. For more information on how Atlantic Canada is poised to benefit from clean energy tax credits, check out part 5 of this series.
Bids
Deadline for submitting bids has been extended to March 23, 2023.
Successful Bidders will be awarded the exclusive right to pursue their project through the Crown Lands and Environmental Assessment processes.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership.
[1] Using a base case of a 1000 MW Windfarm and a 500 MW Hydrogen (Ammonia) Facility with capital costs of $3.5 billion with an annual production of 60k tonnes of hydrogen converted to 344k tonnes of ammonia.
Archive
Included in Discovery: Atlantic Education & the Law – Issue 08 Nancy Rubin, QC and Jennifer Taylor More than ever, many of our meetings, classes, presentations and personal communications are happening virtually. With this…
Read MoreErin Best and Giles Ayers Earlier today the Supreme Court of Canada released a unanimous decision in Corner Brook (City) v. Bailey. The case was successfully argued by Erin Best and Giles Ayers of…
Read MoreJoe Thorne, with the assistance of Stuart Wallace (summer student) In a bankruptcy, there is inevitable conflict between all manner of creditors with competing claims. Our federal and provincial legislatures have identified certain claims as…
Read MoreIncluded in Discovery: Atlantic Education & the Law – Issue 08 Lara Greenough In the recent decision of Longueépée v University of Waterloo, 2020 ONCA 830, the Ontario Court of Appeal found the University of…
Read MoreIncluded in Discovery: Atlantic Education & the Law – Issue 08 Sheila Mecking and Evan MacKnight More than a year has passed since the Coronavirus disease (“COVID-19”) arrived in Atlantic Canada and caused all in-person…
Read MoreAnnie Gray and Dante Manna The federal government has announced that the Pay Equity Act (“Act”) will come into force on August 31, 2021. It has also published the final version of the Pay Equity Regulations (“Regulations”), to come into effect on the…
Read MoreSara Espinal Henao Nova Scotia is thriving. Having reached an all-time population high of 979,115 in 2020 and established itself as a start-up center and a top location for businesses, the province is poised for…
Read MoreWe are pleased to present the sixth installment of Beyond the border, a publication aimed at providing the latest information to clients about new programs and other immigration-related information that may be pertinent to employers…
Read MoreLara Greenough and Sheila Mecking Board members, directors, committee members, employees and anyone acting for a regulatory body or under its governing legislation, all have the obligation to act and make decisions in good faith.…
Read MoreWe are pleased to present the eighth issue of Discovery, our very own legal publication targeted to educational institutions in Atlantic Canada. With COVID-19 vaccines rolling out across the country, a renewed sense of hope is…
Read More