The Winds of Change (Part 7): Paying the Piper: New Newfoundland and Labrador Fiscal Framework expects billions in revenues from wind to hydrogen projects
By Dave Randell, G. John Samms, and Stuart Wallace
With the deadline for bids on crown lands available for wind energy projects extended to noon on March 23rd, the latest development in our Winds of Change series looks at the recently announced fiscal framework of Wind-Hydrogen projects in Newfoundland & Labrador
On February 23, 2023, the Newfoundland and Labrador Department of Industry, Energy and Technology announced further information on the fiscal framework of Wind-Hydrogen projects. This article sets out to provide a basic outline the specifics of the framework.
Principles
Predictability and transparency are the intended principles on which the fiscal framework has been developed. This is intended allow investors to make informed decisions. The framework attempts to balance the risk of investment with the use of provincial resources.
Payment Components
For a singular project over a 30-year period, the government of Newfoundland and Labrador expects $3.5B in taxes, royalties and fees.[1]
Payments will occur early in the project, and throughout the operation phase. These payments can be broken into three components: Land, Wind, and Water.
Land
- Crown Land Reserve Fee: Annual charge of 3.5% of the market value of reserved lands. Payments begin upon award of exclusive right to pursue projects on lands.
- Crown Land Lease Fee: Annual charge of 7% of market value of land. Payments begin upon issuance of Crown Land lease.
Wind
- Wind Electricity Tax: Annual charge of $4,000 per megawatt on installed capacity. Payments begin when the turbines are “in-service”, and applicable to all wind-hydrogen projects (≥ 5 megawatts) producing electricity for the purposes of producing hydrogen.
Water
- Water Use Fee: Annual charge of $500 per 1000m3 of water licensed and used, and $50 per 1000m3 of water licensed but not used. Payments begin when permit is issued, and are applicable to all hydrogen facilities.
- Water Royalty: Payable based on the calculated residual value of the water. Rates are tiered and linked to cost recovery. These terms can be modified via agreements with the Province. Further details about calculation in document.
- Tier 1: Rate of 10% applied after 1x cost recovery.
- Tier 2: Rate of 20% applied after 2x cost recovery.
- Tier 3: Rate of 25% applied after 3x cost recovery.
Taxes
Taxes will be applicable to all wind projects producing electricity for the purposes of producing hydrogen. For more information on how Atlantic Canada is poised to benefit from clean energy tax credits, check out part 5 of this series.
Bids
Deadline for submitting bids has been extended to March 23, 2023.
Successful Bidders will be awarded the exclusive right to pursue their project through the Crown Lands and Environmental Assessment processes.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership.
[1] Using a base case of a 1000 MW Windfarm and a 500 MW Hydrogen (Ammonia) Facility with capital costs of $3.5 billion with an annual production of 60k tonnes of hydrogen converted to 344k tonnes of ammonia.
Archive
By: David F. Slipp and Levi Parsche In May 2022, Bill 96 was adopted by Quebec’s National Assembly, significantly amending the Charter of the French Language (the “Charter“). The amendments create new requirements for using…
Read MoreBy Dave Randell, G. John Samms, and Stuart Wallace With the deadline for bids on crown lands available for wind energy projects extended to noon on March 23rd, the latest development in our Winds of…
Read MoreBy Kevin Landry and Colton Smith The Retail Payment Activities Regulations have been released in the Canada Gazette Part 1 for comment. Interested persons may make representations concerning the proposed regulations for a period of 45…
Read MoreBy Andrew Burke, Colleen Keyes, Gavin Stuttard and David Slipp With proxy season once again approaching, many public companies are in the midst of preparing their annual disclosure documents and shareholder materials for their annual…
Read MoreBy Brittany Trafford and Sean Corscadden In response to the nationwide labour shortage, the Federal government is allowing select family members of foreign workers to apply for open work permits. This temporary policy came into…
Read MoreMark Tector and Ben Currie Effective January 1, 2023, amendments to Ontario’s Employment Standards Act, 2000 (“ESA”) took effect, excluding “business consultants” and “information technology consultants” from the application of the ESA. This is a…
Read MoreBy Perlene Morrison, K.C. and Curtis Doyle Once again, the time has come to review the year that was and to chart the course for the year ahead. For municipalities and planning professionals in Prince…
Read MoreBy Grant Machum ICD.D, Sean Kelly & Ben Currie As the window for “Happy New Year” wishes winds down, our Labour and Employment Group has compiled an overview of emerging trends and issues in workplace…
Read MoreWednesday’s Thought Leadership piece from our Immigration Group detailed the impacts of recent Federal legislation limiting housing purchases by non-Canadians on Foreign Nationals, international students and temporary and permanent residents. Today, lawyers from our Real…
Read MoreBy Brendan Sheridan Residential housing prices in Canada have been a major area of concern for many Canadians who have been looking to purchase a home in recent years. While the market for residential homes…
Read More