The Winds of Change (Part 6): Place your bids – Crown lands soon to be available for wind energy projects
By John Samms, Stuart Wallace and Dave Randell
On December 14, 2022, the Newfoundland and Labrador Department of Industry, Energy and Technology announced the launch of a Crown land call for bids for wind energy projects. The document Guidelines: Crown Land Calls for Bids for Wind Energy Projects outlines the information required for bidders, including evaluation criteria. While the document should be reviewed for complete details of the process, this article is intended to provide a brief overview of the process.
Call for Bids
Bids can now be submitted for wind developments on Crown lands, and will be accepted from December 14, 2022 until midnight on March 3, 2023. Bids must be submitted via email to the Department of Industry, Energy and Technology. Available Crown lands for these projects can be viewed here.
Information for Evaluation
Bidders will be expected to provide, among other things, the following information for evaluation:
- Project summary;
- Associated Hydrogen/Ammonia production;
- Water requirements;
- Project risk mitigation;
- Electricity considerations and grid impacts;
- Community and Indigenous engagement;
- Project schedule; and,
- Financing.
Legislation
It is imperative that bidders review the province’s legislative and regulatory frameworks, including, but not limited to, those pertaining to the development and provision of electricity in the province, such as, the Public Utilities Act and the Electrical Power Control Act, 1994.
Evaluation of Bids
There will be a two-phased evaluation of bids.
Phase 1 Review – Minimum Criteria
First Stage Review will evaluate whether submissions meet the minimum criteria expected of a bidder to be able to deliver a Wind Energy Project. Emphasis will be placed on the bidder’s experience, the project, and their financial capacity to plan, construct, and operate the proposed project.
Phase 2 Review
Those successful in Phase 1 will automatically proceed to a Phase 2 review. This will begin in April 2023. This will be a more robust evaluation focused on the entirety on the information provided. The second stage review involves a weighted evaluation system, whereby electricity considerations and grid impacts are evaluated as heavily as bidder details, project details, benefits, and financing. The weighting is listed as follows:
- Bidder: 15%
- Project Risk Mitigation: 5%
- Electricity Considerations and Grid: 15%
- Community and Indigenous Engagement: 10%
- Benefits: 15%
- Project Schedule: 10%
- Financing: 10%
Successful Bidders
Successful bidders will not be awarded Crown land at the outset. Instead, the province utilized mechanisms under the Lands Act to proactively reserve certain lands to later grant successful proponents the exclusive right to formally apply for an interest in the property. The provincial government will then provide successful proponents a wind application recommendation letter from the Department. This will serve as the instrument that guarantees a proponent an exclusive window to secure relevant Crown land, subject to the various legislation including the Public Utilities Act and the Electrical Power Control Act, 1994.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership
Archive
Rick Dunlop In my December 15, 2016 article, Federal Government’s Cannabis Report: What does it mean for employers?, I noted the Report’s1 suggestion that there was a lack of research to reliably determine when individuals are impaired…
Read MoreRick Dunlop and Michelle Black On March 14, 2014, CanMar Contracting Limited (“CanMar”) granted a day off to two of its hard working and longer serving employees so they could spend time with their respective families. That…
Read MoreJoe Thorne and Meaghan McCaw The doctrine of unconscionability is an equitable remedy available in exceptional circumstances where a bargain between parties, be it a settlement or a release, may be set aside on the basis that…
Read MoreJonathan Coady After more than five years, the Prince Edward Island Information and Privacy Commissioner (the “Privacy Commissioner”) has completed her review into more than sixty records withheld by a local school board on the…
Read MorePeter McLellan, QC & Richard Jordan Introduction On February 21, 2017 the Nova Scotia Government passed Bill 75 – the Teachers’ Professional Agreement and Classroom Improvement (2017) Act. This Bulletin will provide some background to what is, today,…
Read MoreBruce Grant, QC and Justin Hewitt In the recent decision of Scotia Mortgage Corporation v Furlong1 the Supreme Court of Newfoundland and Labrador confirmed that where a law firm acts jointly for the borrower and lender in the placement…
Read MoreThe Supreme Court of Canada released its decision in Sabean v Portage La Prairie Mutual Insurance Co, 2017 SCC 7 at the end of January, finally answering an insurance policy question that had divided the lower…
Read MoreIn preparing for the 2017 proxy season, you should be aware of some regulatory changes and institutional investor guidance that may impact disclosure to, and interactions with, your shareholders. This update highlights what is new…
Read MorePerlene Morrison and Hilary Newman During the fall 2016 legislative sitting, the Province of Prince Edward Island passed legislation that results in significant changes to the Planning Act. The amendments received royal assent on December 15, 2016 and…
Read MoreJoe Thorne1 and Justin Hewitt2 In Unifund Assurance Company v Churchill,3 the Newfoundland and Labrador Court of Appeal considered the application of our rules of court and the common law as they relate to disclosure of documents produced in…
Read More