Let’s talk about batteries: Nova Scotia Power’s latest development in renewable energy

In conjunction with our upcoming sponsorship of the Halifax Chamber of Commerce luncheon, featuring the Minister of Energy and Natural Resources the Hon. Jonathan Wilkinson, we are pleased to present a Thought Leadership article highlighting one of the many renewable energy topics to be discussed. 


By Nancy Rubin and Marina Luro[1]

In a promising new development for Nova Scotia’s transition to renewable energy, the Nova Scotia Utility and Review Board (“NSUARB”) recently approved NS Power’s plan to build three battery energy storage systems (“BESS”) adjacent to existing substations.

Toward a renewable Nova Scotia

Under Nova Scotia’s Clean Energy Plan, the province aims to phase out the use of coal and achieve 80 per cent renewable energy by 2030, thereby reducing greenhouse gas emissions and propelling Nova Scotia into a green future. The Plan contemplates development of substantial amounts of renewable energy, including through wind and solar technology.

As every Nova Scotian well knows, Nova Scotia is windy. Onshore and offshore wind capacity creates great potential for Nova Scotia to harness wind and convert it into green energy. The Clean Energy Plan aims to add 1,000 MW of new wind energy by 2030, in addition to the 370 MW already in the works.

Batteries are required to maintain power and ensure grid stability while adding substantial amounts of wind energy to the system, which is inherently variable and dependent on nature. To facilitate and encourage this, the Government of Nova Scotia amended the Nova Scotia Electricity Act, adding section 4D(9), with regulation-making power to prescribe an energy-storage project. The Governor in Council passed the Prescribed Energy-Storage Projects Regulations, December 21, 2023, which provides that the NS Power BESS Project is a prescribed battery-energy project, and sets out certain requirements for the Project.

Taking a closer look at BESS

The Regulations specify NS Power’s BESS project of three, 50 MW 4-hour duration lithium-ion grid-scale batteries with an electricity storage energy rating of 200 MWh each. Each battery must be housed in a separate facility, adjacent to existing substations at (i) Bridgewater, Lunenburg County; (ii) White Rock Road, Kings Country; and (iii) Spider Lake, Halifax County.

NS Power submitted a proposed plan for the BESS Project to the NSUARB for approval of the capital expenditure. The BESS Project will have the following key features:

  • Dispatchable, firm capacity – The BESS can provide continuous and reliable energy for four hours at full output (150 MW) to meet peak demands, or at lower output for 12 hours.
  • Energy time shifting or arbitrage – The BESS has the ability to store low-cost energy generated off-peak to use during on-peak hours. The BESS typically will charge during high wind/low usage periods, generally overnight, and use that energy to meet the demands of the low wind/high usage periods generally experienced in the mornings.
  • Grid frequency and voltage support – The ability to maintain grid stability by sensing and responding to fluctuations in system frequency thereby mitigating the effects of voltage spikes and dips.
  • Spinning reserve – The ability to respond quickly to unexpected grid changes, through spinning reserve – an online generation capacity that is synchronized with the grid to allow for near instantaneous responses to disruptions.
  • Grid flexibility through response to controlled setpoints – The NS Power System Operator (and after transition, the new Independent Energy System Operator) will be able to ensure that the system frequency remains within the limits established by the Energy Control Centre by setting power levels for the BESS to automatically respond to.

The total cost for the BESS Project is estimated to be $354 million. However, NS Power received approximately $116.6 million in funding from the Federal Government through Natural Resources Canada’s Smart Renewables and Electrification Pathways (“SREP”) Program, and from Natural Resources Canada’s Electricity Predevelopment Program (“EPP”), thereby reducing the cost to ratepayers to $237.7 million.

The NSUARB approved the BESS Project on June 13, 2024, finding that it is “necessary” as it is required to meet the Regulation, and that the cost of the Project is justified and reasonable, and it aligns with government environmental policies and targets.  The NSUARB did impose reporting obligations on NS Power to ensure the Project remains on track. The Project is being developed under an Engineering, Procurement and Construction (“EPC”) contract and on July 2, 2024, NS Power executed an EPC agreement with e-STORAGE, which is part of the Canadian Solar Inc.’s majority-owned subsidiary CSI Solar Co. Ltd.

NS Power plans to have two of the three sites up and running in 2025, with the third running in 2026. This puts Nova Scotia on the right track to reaching its goal of phasing out coal and transitioning to 80 per cent renewable energy by 2030.


This client update is provided for general information only and does not constitute legal advice. If you have any questions about the above, please contact a member of our Energy Group.

Click here to subscribe to Stewart McKelvey Thought Leadership.

[1] At time of publication, Marina Luro was employed with the Firm as a summer student.

SHARE

Archive

Search Archive


 
 

Inside your domain: fighting domain name abuse

March 16, 2022

Brendan Peters Domain names are the addresses we type into our internet browsers to be taken to a website, like ‘stewartmckelvey.com’. Even easy-to-remember domain names can be confused with similar ones, making them a vector…

Read More

Amendments to come for more flexibility to correct contribution errors in defined contribution plans

March 7, 2022

Level Chan and Rachel Abi Daoud On February 4, 2022 the federal government released a set of draft legislative proposals (“Draft Legislation”) amending the Income Tax Act (“Act“) and Income Tax Regulations (“Regulations“). The draft…

Read More

Employers of foreign nationals: LMIA compliance inspections

March 4, 2022

Included in Beyond the border: Immigration update – February 2022 Brittany Trafford There are many advantages to employing temporary foreign workers (“TFW”) in Canada to address labour gaps and skills shortages, but employers who undertake…

Read More

LMIA advertising exemptions

March 2, 2022

Included in Beyond the border: Immigration update – February 2022 Brendan Sheridan The majority of foreign nationals coming to work in Canada require a work permit to provide their services with limited exceptions. While there…

Read More

An end to vaccine mandates? Considerations for employers

March 1, 2022

Mark Tector and Will Wojcik On February 23rd, 2022, the Government of Nova Scotia announced that it will remove all public health restrictions by March 21, 2022, putting an end to approximately two years of…

Read More

New Brunswick COVID-19 policies and procedures: where do we go from here? / Les politiques et procédures COVID-19 au Nouveau-Brunswick : où en sommes-nous ?

February 25, 2022

Provincial mandates, and the advice of public health have required employers to constantly adapt and implement changes to their workplace for the better part of the last two years – it isn’t over yet. Revocation…

Read More

LMIA recruitment tracking

February 25, 2022

Included in Beyond the border: Immigration update – February 2022 Brendan Sheridan Employers applying for Labour Market Impact Assessment (“LMIA”) applications generally must complete advertising and recruitment as part of this application. The minimum advertising…

Read More

The Atlantic Immigration Program – now a permanent pathway for immigration

February 24, 2022

Included in Beyond the border: Immigration update – February 2022 Sara Espinal Henao The Atlantic Immigration Pilot Program has finally become a permanent immigration pathway. Designated employers in Atlantic Canada will be able to continue…

Read More

Outlook for 2022 proxy season

February 18, 2022

Andrew Burke, Colleen Keyes, Gavin Stuttard and David Slipp As clients prepare for the upcoming proxy season, COVID-19 continues to impact our business and personal lives. Consequently, companies may need or decide to hold shareholder…

Read More

Federal regulations impose new requirement for employers to provide annual report on workplace violence and harassment by March 1

February 17, 2022

Katharine Mack On January 1, 2021 the Workplace Harassment and Violence Prevention Regulations (“Regulations”) under the Canada Labour Code came into effect.  These Regulations significantly expanded obligations of federally regulated employers with respect to preventing…

Read More

Search Archive


Scroll To Top