Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Client Update: Requirement to register as a mortgage brokerage and mortgage administrator in New Brunswick

July 7, 2016

On April 1, 2016 New Brunswick’s Mortgage Brokers Act came into force, requiring businesses acting as mortgage brokerages or as mortgage administrators in New Brunswick to be licensed. A mortgage brokerage is a business that on behalf…

Read More

Copyright does not monopolize facts – documentary filmmakers’ claim against book author and publisher fails

June 29, 2016

In May 2016, the Federal Court of Canada confirmed that copyright does not protect facts, even where a book’s author is clearly inspired by the content of a film (Maltz v. Witterick, 2016 FC 524 (CanLII)).…

Read More

Solicitor-client privilege vs the Canada Revenue Agency: the SCC speaks

June 10, 2016

By Jennifer Taylor “…firms of notaries or lawyers…must not be turned into archives for the tax authorities”1 So says the Supreme Court of Canada in one of two highly anticipated decisions on solicitor-client privilege, offering lawyers…

Read More

Why can’t we be friends?: Lessons on corporate dissolution from Smith v. Hillier

May 30, 2016

Joe Thorne1 and Clara Linegar2 As joint owners of a business, what do you do when the business relationship falls apart? And what if one owner undermines the business in the process? In Smith v Hillier,3 Justice Paquette…

Read More

Client Update: Supreme Court of Canada dismisses appeals in punitive damages cases

May 26, 2016

The Supreme Court of Canada has dismissed the appeals in Bruce Brine v. Industrial Alliance Insurance and Financial Services Inc.1 (with costs) and Luciano Branco, et al. v. Zurich Life Insurance Company Limited, et al.(without costs). Both of…

Read More

Client Update: Pension update: Countdown to Nova Scotia Pooled Registered Pension Plans

May 17, 2016

On May 4, 2016, the Nova Scotia Pooled Registered Pension Plans Act (“PRPP Act”) was proclaimed in force, and finalized Pooled Registered Pension Plan Regulations were released. While there were no major changes from the previously released draft regulations, the proposed rules…

Read More

Pension Primer: Pooled Registered Pension Plans (“PRPPs”) in Nova Scotia

April 22, 2016

By Level Chan and Dante Manna Pooled Registered Pension Plans (“PRPPs”) are closer to becoming a reality for Nova Scotian employers. PRPPs were established by the Federal government in an effort to address the lack of retirement savings…

Read More

Client Update: Perrin v Blake reaffirms the law on contributory negligence and recovery of damages

April 14, 2016

In a case where there is a contributorily negligent plaintiff and two or more negligent defendants, can the plaintiff recover 100% of her damages from any of the defendants? The answer in Nova Scotia is…

Read More

Client Update: Interest arbitration changes for New Brunswick postponed for further study

April 11, 2016

On Friday, the Province of New Brunswick announced that it would not proceed at this time with the recently proposed changes to binding interest arbitration. The Province announced that a joint labour management committee will be struck to examine…

Read More

Client Update: Universal interest arbitration proposed for New Brunswick

April 5, 2016

On March 29, 2016, the Province of New Brunswick tabled proposed changes to the Industrial Relations Act and the Public Services Labour Relations Act. If passed, these changes would dramatically alter well-established principles of private sector collective bargaining.…

Read More

Search Archive


Scroll To Top