Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Surprise changes to Nova Scotia’s minimum wage and partial hours rules announced

January 30, 2020

Jennifer Thompson Nova Scotia’s Premier’s Office has today made an unexpected announcement regarding several changes to be made to Nova Scotia’s minimum wage and partial hours rules, with effect from April 1, 2020. Additional increase…

Read More

My PR Card expired! What do I do?

January 28, 2020

Kathleen Leighton For individuals whose Permanent Resident Cards (“PR Cards”) have expired, it can be a time of panic. “Did I lose my status?”, “Do I have to leave the country immediately?”, “Can I still…

Read More

Input sought on Nova Scotia pension division and other family property matters

January 24, 2020

Dante Manna The Nova Scotia Government is seeking input by way of public survey or written submissions on proposed changes to family property law that would, among other things, affect pension division between former spouses.…

Read More

Atlantic Canada Year in Review 2019 – Top 15 Takeaways for Employers

January 23, 2020

Atlantic Canada experienced a number of legal developments in 2019 that regional employers should be aware of as they plan for the year ahead. Click the image below to read our 2019 year in review,…

Read More

Supreme Court of Canada’s Canada Post decision delivers good news for federal employers

January 20, 2020

G. Grant Machum & Richard Jordan On December 20, 2019, the Supreme Court of Canada released its decision in Canada Post Corporation v. Canadian Union of Postal Workers, 2019 SCC 67.  This case involved a…

Read More

Atlantic Canada pension and benefits outlook 2020

January 13, 2020

Level Chan and Dante Manna In this update we provide what we see on the employee benefits and pension plans legal horizon in 2020 and beyond, along with a review of some highlights from 2019.…

Read More

Accessible Canada Act – the beginning of a new era in accessibility?

January 9, 2020

Jennifer Thompson The Accessible Canada Act (“Act”) came into force on July 11, 2019, ushering in the start of a march towards a Canada without barriers for persons with disabilities. While the Act only applies…

Read More

Five compliance tips (for employers of foreign workers)

January 7, 2020

Kathleen Leighton If you employ an individual who holds a work permit to authorize their work in Canada, you likely have various obligations to adhere to and can face significant consequences if your business is…

Read More

Provincial Law Voids Limitations of Liability in Contract for Ship’s Engine Parts

January 7, 2020

David Constantine and Joe Thorne In the recent Supreme Court of Canada decision in Desgagnés Transport Inc v Wärtsilä Canada Inc, 2019 SCC 58, the court examined how provincial statutes and the federal maritime law…

Read More

2019 intellectual property year in review

January 6, 2020

Daniela Bassan Noteworthy cases Keatley Surveying Ltd. v. Teranet Inc., 2019 SCC 43 Considering Crown copyright for the first time, the Supreme Court of Canada upheld the dismissal of a class action brought by land…

Read More

Search Archive


Scroll To Top