Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Canada’s carbon tax – an increase and a refresher

January 14, 2021

Kevin Landry and William Wojcik On December 11, 2020, the federal government announced Canada’s strengthened climate plan in a document titled A Healthy Environment and a Healthy Economy (“Plan”). The Plan proposes to increase the carbon…

Read More

The end of the Mechanics’ Lien Act

January 13, 2021

Kenneth McCullogh, QC and Conor O’Neil, P.Eng. On December 18, 2020, the Legislative Assembly of New Brunswick passed the Construction Remedies Act. The new legislation will not take effect until a date to be named…

Read More

Communication breakdown: Offensive comments can constitute cause under Canada Labour Code

January 13, 2021

Mark Tector In a recent decision, an adjudicator upheld the dismissal of an employee/complainant who made inappropriate and offensive remarks on a call with a customer (Crawford v Canadian Imperial Bank of Commerce). The complainant…

Read More

2020 Year in Review: Atlantic Canada Labour & Employment Law Developments

January 11, 2021

2020 brought us all challenges that have been unprecedented in our time. The COVID-19 global pandemic has impacted us in ways that were unimaginable. As Atlantic Canada navigated the challenges of changing worlds, and workplaces,…

Read More

New pre-boarding COVID-19 testing requirements

January 7, 2021

Kathleen Leighton On December 31, 2020, the Honourable Marc Garneau, Minister of Transport, announced new pre-boarding COVID-19 testing requirements that would be coming into effect in short order. In particular, as of January 6, 2021…

Read More

La Dolce Vita and design: Italian Court confirms copyright of concept store

January 6, 2021

Daniela Bassan, QC, has published an article in volume 36 of the Canadian Intellectual Property Review. She comments on an Italian case granting copyright protection for a retail store in the cosmetics industry, and considers…

Read More

Duty of honest performance in termination of commercial contracts – the Supreme Court of Canada elaborates in Callow v. Zollinger, 2020 SCC 45

January 4, 2021

Rob Aske In late December 2020, the Supreme Court of Canada (“SCC”) issued a key decision elaborating on the duty of honesty in relation to termination of a commercial contract. This duty was primarily established…

Read More

Ongoing flexibility for international students due to COVID-19

December 29, 2020

Included in Discovery: Atlantic Education & the Law – Issue 07 Kathleen Leighton Educational institutions and their students continue to face challenges as a result of the COVID-19 pandemic, and international students are particularly impacted…

Read More

Institutional responsibility to prepare for COVID-19 cases on campus

December 23, 2020

Included in Discovery: Atlantic Education & the Law – Issue 07 Kate Jurgens Since returning to class in September amidst the uncertainty of the COVID-19 global pandemic, students and faculty alike in classrooms, on campus,…

Read More

Increasing pay transparency for federally regulated employers under Employment Equity Regulations

December 18, 2020

Brian G. Johnston, QC, Jennifer Thompson and Daniel Roth The Government of Canada has announced the final Regulations Amending the Employment Equity Regulations (“Regulations”). The Regulations come into force on January 1, 2021 and will bring increased pay transparency to federally regulated…

Read More

Search Archive


Scroll To Top