Skip to content

Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Digital Charter Implementation Act, 2020: The long-awaited overhaul of private sector privacy legislation in Canada

November 20, 2020

Koren Thomson and Sarah Byrne On November 17, 2020, the Digital Charter Implementation Act, 2020 (“Act”) was introduced as Bill C-11. This is the first major update to the federal private sector privacy regime in…

Read More

Federal Pay Equity Regulations published in draft – key takeaways

November 20, 2020

Jennifer Thompson The Federal Government has released draft Regulations under the Pay Equity Act (“the Act”), almost 11 months after the Act received Royal Assent. The Act, which is not yet in force, makes significant…

Read More

What steps must employers take to hire a foreign worker?

November 16, 2020

Kathleen Leighton Employers often wonder what steps they need to take to hire international talent, including what support they must provide to enable a foreign worker to obtain proper work authorization in Canada. This is…

Read More

How to improve your Express Entry score

October 30, 2020

Kathleen Leighton Express Entry system Express Entry is a system that enables skilled foreign nationals who are looking to settle in Canada indefinitely to apply for permanent residency status. This system prioritizes individuals who are…

Read More

COVID-19: Federal government announces continuing package of pandemic supports

October 29, 2020

Katharine Mack The federal government has recently announced a series of changes to be made to benefit programs rolled out in response to the COVID-19 pandemic. The extension or expansion of these benefits and support…

Read More

Federal work place harassment and violence prevention regulations

October 26, 2020

Chad Sullivan and Kathleen Nash In late June 2020, the Federal Government released the official version of the new Work Place Harassment and Violence Prevention Regulations¹ (“Regulations”) along with Bill C-65, the federal anti-harassment and…

Read More

Canada’s bid to attract entrepreneurs: the Start-up Visa Program

October 16, 2020

Sara Espinal Henao Canada wants entrepreneurs. With a strong and stable economy, world leading growth opportunities across industries, and a highly educated workforce, it is a great place to build a dynamic business that can…

Read More

The million dollar question: is an employee entitled to a post-termination bonus payment?

October 9, 2020

Killian McParland Earlier today, the Supreme Court of Canada released a new decision with significant implications for employers in Matthews v. Ocean Nutrition Canada Ltd. While the underlying case came out of Nova Scotia, it…

Read More

The boomerang that won’t come back – Court of Appeal confirms that parties must each bring their own motions for summary judgment

September 25, 2020

Chad Sullivan and Kathleen Nash In a recent decision from the New Brunswick Court of Appeal, Abrams v RTO Asset Management, 2020 NBCA 57, the court clarified the procedure for seeking summary judgment and addresses…

Read More

The limits of open work permits

September 23, 2020

Kathleen Leighton In Canada, foreign nationals have various options to obtain either “employer-specific” or “open” work permits – we discuss this distinction in greater detail here. Open work permits can be obtained by individuals in…

Read More

Search Archive


Scroll To Top