Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Zoning changes and constructive taking: Newfoundland and Labrador Court of Appeal affirms the finding in Index v Paradise

August 28, 2024

Stephen Penney and Megan Kieley1 The Newfoundland and Labrador Court of Appeal’s recent decision in Index Investments Inc v Paradise (Town)2 is a significant decision for municipalities. The Court of Appeal endorsed the Newfoundland and…

Read More

Immigration red flags: five organizational issues that open employers to risk

August 15, 2024

By Kathleen Leighton & Brittany Trafford The Temporary Foreign Worker Program (“TFWP”) and International Mobility Program (“IMP”) provide Canadian employers the opportunity to hire foreign workers to address their labour needs, particularly when qualified Canadians…

Read More

Supreme Court of Canada denies leave to appeal of Alberta ruling on post-death life insurance conversion (Part II)

August 15, 2024

This is the second in a two-part Thought Leadership series on a recent life insurance case out of Alberta, and the implications for life insurers. Michelle Chai and Liz Campbell1 Part I of this two-part series…

Read More

Changing the rules again: Another round of changes impacting Canada’s Competition Act

August 14, 2024

By Deanne MacLeod, K.C., Burtley G. Francis, K.C., and David F. Slipp On June 20, 2024 the Fall Economic Statement Implementation Act, 2023 (the “Economic Statement”) received Royal Assent and became law. The Economic Statement…

Read More

Supreme Court of Canada denies leave to appeal of Alberta ruling on post-death life insurance conversion

August 13, 2024

This is the first in a two-part Thought Leadership series on a recent life insurance case out of Alberta, and the implications for life insurers. By Michelle Chai and Liz Campbell1 The Supreme Court of…

Read More

Canada’s investment in hydrogen has substantial implications for the Atlantic Canadian wind power sector

August 6, 2024

This articles follows our recent Thought Leadership piece on the Federal Government’s announcement of significant investment through the Smart Renewables and Electrification Pathways Program in Nova Scotia clean energy projects. By Dave Randell, Sadira Jan,…

Read More

New announcements in the Canada-Nova Scotia partnership for the clean energy future

August 1, 2024

By David Randell, Sadira E. Jan, Daniel Mowat-Rose, and Marina Luro1 Natural Resources Canada has released two important announcements relating to Nova Scotia’s transition to a green economy: Collaboration framework for a sustainable future Canada’s…

Read More

Workplace investigation helps avoid costly litigation

July 29, 2024

By Sheila Mecking and Lauren Sorel The British Columbia Human Rights Tribunal (“BCHRT”) recently dismissed a complaint of discrimination in the workplace, stating that the employer’s investigation, and settlement offer, adequately resolved the complaint.1 The …

Read More

Cybersecurity class actions against database defendants persist, but hurdles for plaintiffs remain

July 25, 2024

By Sarah Dever Letson, CIPP/C, Meaghan McCaw and Bertina Lou[1] Two decisions earlier this month from the Court of Appeal for British Columbia left open the question as to whether so-called “database defendants” can be held…

Read More

Let’s talk about batteries: Nova Scotia Power’s latest development in renewable energy

July 18, 2024

In conjunction with our upcoming sponsorship of the Halifax Chamber of Commerce luncheon, featuring the Minister of Energy and Natural Resources the Hon. Jonathan Wilkinson, we are pleased to present a Thought Leadership article highlighting…

Read More

Search Archive


Scroll To Top