On December 14, 2022, the Newfoundland and Labrador Department of Industry, Energy and Technology announced the launch of a Crown land call for bids for wind energy projects. The document Guidelines: Crown Land Calls for Bids for Wind Energy Projects outlines the information required for bidders, including evaluation criteria. While the document should be reviewed for complete details of the process, this article is intended to provide a brief overview of the process.
Call for Bids
Bids can now be submitted for wind developments on Crown lands, and will be accepted from December 14, 2022 until midnight on March 3, 2023. Bids must be submitted via email to the Department of Industry, Energy and Technology. Available Crown lands for these projects can be viewed here.
Information for Evaluation
Bidders will be expected to provide, among other things, the following information for evaluation:
- Project summary;
- Associated Hydrogen/Ammonia production;
- Water requirements;
- Project risk mitigation;
- Electricity considerations and grid impacts;
- Community and Indigenous engagement;
- Project schedule; and,
- Financing.
Legislation
It is imperative that bidders review the province’s legislative and regulatory frameworks, including, but not limited to, those pertaining to the development and provision of electricity in the province, such as, the Public Utilities Act and the Electrical Power Control Act, 1994.
Evaluation of Bids
There will be a two-phased evaluation of bids.
Phase 1 Review – Minimum Criteria
First Stage Review will evaluate whether submissions meet the minimum criteria expected of a bidder to be able to deliver a Wind Energy Project. Emphasis will be placed on the bidder’s experience, the project, and their financial capacity to plan, construct, and operate the proposed project.
Phase 2 Review
Those successful in Phase 1 will automatically proceed to a Phase 2 review. This will begin in April 2023. This will be a more robust evaluation focused on the entirety on the information provided. The second stage review involves a weighted evaluation system, whereby electricity considerations and grid impacts are evaluated as heavily as bidder details, project details, benefits, and financing. The weighting is listed as follows:
- Bidder: 15%
- Project Risk Mitigation: 5%
- Electricity Considerations and Grid: 15%
- Community and Indigenous Engagement: 10%
- Benefits: 15%
- Project Schedule: 10%
- Financing: 10%
Successful Bidders
Successful bidders will not be awarded Crown land at the outset. Instead, the province utilized mechanisms under the Lands Act to proactively reserve certain lands to later grant successful proponents the exclusive right to formally apply for an interest in the property. The provincial government will then provide successful proponents a wind application recommendation letter from the Department. This will serve as the instrument that guarantees a proponent an exclusive window to secure relevant Crown land, subject to the various legislation including the Public Utilities Act and the Electrical Power Control Act, 1994.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership
Archive
Newfoundland and Labrador adopts virtual Alternate Witnessing of Documents Act – for good this time!
By Joe Thorne and Megan Kieley Background During the COVID-19 public health emergency order in Newfoundland and Labrador, the government passed the Temporary Alternate Witnessing of Documents Act, which (as the name implies) temporarily permitted…
Read MoreBy Daniela Bassan, K.C. Daniela Bassan, K.C. is a Partner and Practice Group Chair at the law firm of Stewart McKelvey (Canada) where she focuses on intellectual property and complex, multi-jurisdictional dispute resolution. The premise…
Read MoreBy Conor O’Neil and Maria Cummings On May 9, 2023, two bills were introduced in the New Brunswick Legislature that could have material affects on the construction industry. Bills 41 and 42, of the current…
Read MoreAuthor Sara Espinal Henao, an Immigration Lawyer in our Halifax office, will be speaking on a related panel, Labour Market Impact Assessments Overview and Current Trends, at the upcoming CBA Immigration Law Conference in Ottawa,…
Read MoreAuthor Brendan Sheridan, an Immigration Lawyer in our Halifax Office, will be running a related webinar on May 30, 2023, Avoiding immigration bloopers: A webinar for the film & television industry, in partnership with Screen…
Read MoreIncluded in Discovery: Atlantic Education & the Law – Issue 12 By Charlotte Henderson Privacy and confidentiality requirements are some of the most important responsibilities of organizations today. An organization’s ability to properly manage information,…
Read MoreIncluded in Discovery: Atlantic Education & the Law – Issue 12 By Hilary Newman & Jacob Zelman A non-disclosure agreement, or “NDA”, is a legal contract in which two or more persons agree to keep the…
Read MoreBy Graham Haynes & Isaac McLellan Introduction The Canadian federal budget was unveiled on Tuesday, March 28, 2023 (“Budget 2023”)1 , and proposes significant changes to the General Anti-Avoidance Rule (the “GAAR”) in Canadian tax…
Read MoreIncluded in Discovery: Atlantic Education & the Law – Issue 12 By Scott Campbell, Jennifer Taylor, Folu Adesanya A long-standing dispute over governance practices at the Cape Breton University Board of Governors was recently resolved…
Read MoreIncluded in Discovery: Atlantic Education & the Law – Issue 12 By Jon O’Kane & Emma Douglas These days it seems no one is immune from the threat of anonymous keyboard warriors posting untrue and…
Read More