The Winds of Change (Part 6): Place your bids – Crown lands soon to be available for wind energy projects

By John Samms, Stuart Wallace and Dave Randell

On December 14, 2022, the Newfoundland and Labrador Department of Industry, Energy and Technology announced the launch of a Crown land call for bids for wind energy projects. The document Guidelines: Crown Land Calls for Bids for Wind Energy Projects outlines the information required for bidders, including evaluation criteria. While the document should be reviewed for complete details of the process, this article is intended to provide a brief overview of the process.

Call for Bids

Bids can now be submitted for wind developments on Crown lands, and will be accepted from December 14, 2022 until midnight on March 3, 2023. Bids must be submitted via email to the Department of Industry, Energy and Technology. Available Crown lands for these projects can be viewed here.

Information for Evaluation

Bidders will be expected to provide, among other things, the following information for evaluation:

  • Project summary;
  • Associated Hydrogen/Ammonia production;
  • Water requirements;
  • Project risk mitigation;
  • Electricity considerations and grid impacts;
  • Community and Indigenous engagement;
  • Project schedule; and,
  • Financing.

Legislation

It is imperative that bidders review the province’s legislative and regulatory frameworks, including, but not limited to, those pertaining to the development and provision of electricity in the province, such as, the Public Utilities Act and the Electrical Power Control Act, 1994.

Evaluation of Bids

There will be a two-phased evaluation of bids.

Phase 1 Review – Minimum Criteria

First Stage Review will evaluate whether submissions meet the minimum criteria expected of a bidder to be able to deliver a Wind Energy Project. Emphasis will be placed on the bidder’s experience, the project, and their financial capacity to plan, construct, and operate the proposed project.

Phase 2 Review

Those successful in Phase 1 will automatically proceed to a Phase 2 review. This will begin in April 2023. This will be a more robust evaluation focused on the entirety on the information provided. The second stage review involves a weighted evaluation system, whereby electricity considerations and grid impacts are evaluated as heavily as bidder details, project details, benefits, and financing. The weighting is listed as follows:

  • Bidder: 15%
  • Project Risk Mitigation: 5%
  • Electricity Considerations and Grid: 15%
  • Community and Indigenous Engagement: 10%
  • Benefits: 15%
  • Project Schedule: 10%
  • Financing: 10%

Successful Bidders

Successful bidders will not be awarded Crown land at the outset. Instead, the province utilized mechanisms under the Lands Act to proactively reserve certain lands to later grant successful proponents the exclusive right to formally apply for an interest in the property. The provincial government will then provide successful proponents a wind application recommendation letter from the Department. This will serve as the instrument that guarantees a proponent an exclusive window to secure relevant Crown land, subject to the various legislation including the Public Utilities Act and the Electrical Power Control Act, 1994.


This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.

Click here to subscribe to Stewart McKelvey Thought Leadership

 

SHARE

Archive

Search Archive


 
 

Doing Business in Atlantic Canada

May 26, 2014

Download as a PDF

Read More

Doing Business in Atlantic Canada

May 26, 2014

Download as a PDF

Read More

Client Update: Professional Partnerships Breathe Easier

May 22, 2014

This morning the Supreme Court of Canada released its much awaited decision in McCormick v. Fasken Martineau DuMoulin, holding that most legal (and other professional) partnerships are not subject to Human Rights obligations to partners,…

Read More

Client Update: PEI Auto Insurance Reforms: Change is Coming

May 20, 2014

No really. We mean it this time. During the Spring 2014 sitting of the legislature, the PEI government passed legislation that will result in significant changes to the standard automobile policy, effective October 1, 2014. Most…

Read More

Atlantic Employers’ Counsel – Spring 2014

May 8, 2014

The Editor’s Corner Clarence Bennett This edition focuses on employment and labour issues in Construction. From occupational health and safety legislation to what you need to know when the union organizer arrives at your workplace.…

Read More

Client Update: Changes to the Canada Labour Code

March 28, 2014

Federally regulated employers should be aware of changes to the Canada Labour Code (“the Code“) effective April 1, 2014, namely subsections 219 and 223-231 of the Jobs and Growth Act, 2012, chapter 31 of the Statutes of Canada (also…

Read More

Atlantic Insurance Counsel – Winter 2014

March 12, 2014

PEI Auto Accident Benefits – Behind the Times No More Nicole McKenna and Janet Clark Significant changes are coming to the standard automobile policy in Prince Edward Island (“PEI”), including increases to the accident benefits available under…

Read More

Doing Business in Atlantic Canada (Spring 2014)(Canadian Lawyer magazine supplement)

March 3, 2014

 IN THIS ISSUE: 10 Things employers need to know about employing temporary foreign workers by Andrea Baldwin, Michelle McCann and Sean Kelly. Landlords’ protection from mechanic’ (builders’) liens by Hugh Cameron and Lara MacDougall. The new Canada not-for-profit Corporations Act by Alanna Waberski, Sarah Almon and Kimberly Bungay. Download…

Read More

Client Update: Minor Injury Cap 2014

February 27, 2014

On January 31, 2014, The Office of the Superintendent of Insurance issued a bulletin in Nova Scotia. For 2014, the Minor Injury Cap for Nova Scotia is $8,213. This is a 1.4 per cent increase…

Read More

Client Update: The New Building Canada Fund

February 26, 2014

In the Federal Budget 2011, the Government of Canada stated that it would develop a new plan to support public infrastructure beyond the expiry of the 2007 Building Canada Plan in 2013-14. The Government has…

Read More

Search Archive


Scroll To Top