The Winds of Change (Part 6): Place your bids – Crown lands soon to be available for wind energy projects
By John Samms, Stuart Wallace and Dave Randell
On December 14, 2022, the Newfoundland and Labrador Department of Industry, Energy and Technology announced the launch of a Crown land call for bids for wind energy projects. The document Guidelines: Crown Land Calls for Bids for Wind Energy Projects outlines the information required for bidders, including evaluation criteria. While the document should be reviewed for complete details of the process, this article is intended to provide a brief overview of the process.
Call for Bids
Bids can now be submitted for wind developments on Crown lands, and will be accepted from December 14, 2022 until midnight on March 3, 2023. Bids must be submitted via email to the Department of Industry, Energy and Technology. Available Crown lands for these projects can be viewed here.
Information for Evaluation
Bidders will be expected to provide, among other things, the following information for evaluation:
- Project summary;
- Associated Hydrogen/Ammonia production;
- Water requirements;
- Project risk mitigation;
- Electricity considerations and grid impacts;
- Community and Indigenous engagement;
- Project schedule; and,
- Financing.
Legislation
It is imperative that bidders review the province’s legislative and regulatory frameworks, including, but not limited to, those pertaining to the development and provision of electricity in the province, such as, the Public Utilities Act and the Electrical Power Control Act, 1994.
Evaluation of Bids
There will be a two-phased evaluation of bids.
Phase 1 Review – Minimum Criteria
First Stage Review will evaluate whether submissions meet the minimum criteria expected of a bidder to be able to deliver a Wind Energy Project. Emphasis will be placed on the bidder’s experience, the project, and their financial capacity to plan, construct, and operate the proposed project.
Phase 2 Review
Those successful in Phase 1 will automatically proceed to a Phase 2 review. This will begin in April 2023. This will be a more robust evaluation focused on the entirety on the information provided. The second stage review involves a weighted evaluation system, whereby electricity considerations and grid impacts are evaluated as heavily as bidder details, project details, benefits, and financing. The weighting is listed as follows:
- Bidder: 15%
- Project Risk Mitigation: 5%
- Electricity Considerations and Grid: 15%
- Community and Indigenous Engagement: 10%
- Benefits: 15%
- Project Schedule: 10%
- Financing: 10%
Successful Bidders
Successful bidders will not be awarded Crown land at the outset. Instead, the province utilized mechanisms under the Lands Act to proactively reserve certain lands to later grant successful proponents the exclusive right to formally apply for an interest in the property. The provincial government will then provide successful proponents a wind application recommendation letter from the Department. This will serve as the instrument that guarantees a proponent an exclusive window to secure relevant Crown land, subject to the various legislation including the Public Utilities Act and the Electrical Power Control Act, 1994.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership
Archive
Perlene Morrison Prince Edward Island’s municipal legislation is being modernized with the implementation of the Municipal Government Act (the “MGA”). The legislation has now received royal assent and will be proclaimed in force at a future date.…
Read MoreJonathan Coady and Chera-Lee Gomez It’s that time of year – the moment when we look back at the year that was and chart our course for the year ahead. For many councillors, administrators and planning professionals…
Read MorePeter McLellan, QC and Michelle Black In a recent decision, R v McCarthy’s Roofing Limited, Judge Anne Derrick provided some much-needed clarity around what it means to be a “constructor” on a job site. This is critical as…
Read MoreRick Dunlop On December 13, 2016, the Government of Canada released A Framework for the Legalization and Regulation of Cannabis in Canada: The Final Report of the Task Force on Cannabis Legalization and Regulation (“Report”). The Report’s…
Read MoreBrian Johnston, QC Canadian employers are already coping with approximately 75,000 Canadians authorized to use medical marijuana. Health Canada expects that this number will increase to about 450,000 by 2024. Employers know that medical marijuana…
Read MoreJonathan Coady With its decision in Canada Post Corporation v. City of Hamilton,1 the Ontario Court of Appeal has confirmed that the placement of community mailboxes by Canada Post is a matter beyond the reach of municipalities…
Read MoreJennifer Taylor Introduction Thanks to some dirty windows, insurance lawyers have a new go-to Supreme Court case on issues of policy interpretation: Ledcor Construction Ltd v Northbridge Indemnity Insurance Co, 2016 SCC 37. The insurers in Ledcor Construction had…
Read MoreJennifer Taylor Introduction Appeal courts in Ontario1 and Nova Scotia2 have now issued decisions about Trinity Western University’s proposed law school (“TWU”) in British Columbia, and at first glance they couldn’t be more different. The Court of Appeal for…
Read MoreJoe Thorne1 and Giles Ayers2 Limitation periods serve a critical function in the civil justice system. They promote the timely resolution of litigation on the basis of reliable evidence, and permit litigants to assess their legal exposure…
Read MoreOn July 14, 2016 the Supreme Court of Canada issued a significant decision affecting federally regulated employers across Canada. In Wilson v. Atomic Energy of Canada Limited the Court held that the purpose of the unjust dismissal…
Read More