Let’s talk about batteries: Nova Scotia Power’s latest development in renewable energy

In conjunction with our upcoming sponsorship of the Halifax Chamber of Commerce luncheon, featuring the Minister of Energy and Natural Resources the Hon. Jonathan Wilkinson, we are pleased to present a Thought Leadership article highlighting one of the many renewable energy topics to be discussed. 


By Nancy Rubin and Marina Luro[1]

In a promising new development for Nova Scotia’s transition to renewable energy, the Nova Scotia Utility and Review Board (“NSUARB”) recently approved NS Power’s plan to build three battery energy storage systems (“BESS”) adjacent to existing substations.

Toward a renewable Nova Scotia

Under Nova Scotia’s Clean Energy Plan, the province aims to phase out the use of coal and achieve 80 per cent renewable energy by 2030, thereby reducing greenhouse gas emissions and propelling Nova Scotia into a green future. The Plan contemplates development of substantial amounts of renewable energy, including through wind and solar technology.

As every Nova Scotian well knows, Nova Scotia is windy. Onshore and offshore wind capacity creates great potential for Nova Scotia to harness wind and convert it into green energy. The Clean Energy Plan aims to add 1,000 MW of new wind energy by 2030, in addition to the 370 MW already in the works.

Batteries are required to maintain power and ensure grid stability while adding substantial amounts of wind energy to the system, which is inherently variable and dependent on nature. To facilitate and encourage this, the Government of Nova Scotia amended the Nova Scotia Electricity Act, adding section 4D(9), with regulation-making power to prescribe an energy-storage project. The Governor in Council passed the Prescribed Energy-Storage Projects Regulations, December 21, 2023, which provides that the NS Power BESS Project is a prescribed battery-energy project, and sets out certain requirements for the Project.

Taking a closer look at BESS

The Regulations specify NS Power’s BESS project of three, 50 MW 4-hour duration lithium-ion grid-scale batteries with an electricity storage energy rating of 200 MWh each. Each battery must be housed in a separate facility, adjacent to existing substations at (i) Bridgewater, Lunenburg County; (ii) White Rock Road, Kings Country; and (iii) Spider Lake, Halifax County.

NS Power submitted a proposed plan for the BESS Project to the NSUARB for approval of the capital expenditure. The BESS Project will have the following key features:

  • Dispatchable, firm capacity – The BESS can provide continuous and reliable energy for four hours at full output (150 MW) to meet peak demands, or at lower output for 12 hours.
  • Energy time shifting or arbitrage – The BESS has the ability to store low-cost energy generated off-peak to use during on-peak hours. The BESS typically will charge during high wind/low usage periods, generally overnight, and use that energy to meet the demands of the low wind/high usage periods generally experienced in the mornings.
  • Grid frequency and voltage support – The ability to maintain grid stability by sensing and responding to fluctuations in system frequency thereby mitigating the effects of voltage spikes and dips.
  • Spinning reserve – The ability to respond quickly to unexpected grid changes, through spinning reserve – an online generation capacity that is synchronized with the grid to allow for near instantaneous responses to disruptions.
  • Grid flexibility through response to controlled setpoints – The NS Power System Operator (and after transition, the new Independent Energy System Operator) will be able to ensure that the system frequency remains within the limits established by the Energy Control Centre by setting power levels for the BESS to automatically respond to.

The total cost for the BESS Project is estimated to be $354 million. However, NS Power received approximately $116.6 million in funding from the Federal Government through Natural Resources Canada’s Smart Renewables and Electrification Pathways (“SREP”) Program, and from Natural Resources Canada’s Electricity Predevelopment Program (“EPP”), thereby reducing the cost to ratepayers to $237.7 million.

The NSUARB approved the BESS Project on June 13, 2024, finding that it is “necessary” as it is required to meet the Regulation, and that the cost of the Project is justified and reasonable, and it aligns with government environmental policies and targets.  The NSUARB did impose reporting obligations on NS Power to ensure the Project remains on track. The Project is being developed under an Engineering, Procurement and Construction (“EPC”) contract and on July 2, 2024, NS Power executed an EPC agreement with e-STORAGE, which is part of the Canadian Solar Inc.’s majority-owned subsidiary CSI Solar Co. Ltd.

NS Power plans to have two of the three sites up and running in 2025, with the third running in 2026. This puts Nova Scotia on the right track to reaching its goal of phasing out coal and transitioning to 80 per cent renewable energy by 2030.


This client update is provided for general information only and does not constitute legal advice. If you have any questions about the above, please contact a member of our Energy Group.

Click here to subscribe to Stewart McKelvey Thought Leadership.

[1] At time of publication, Marina Luro was employed with the Firm as a summer student.

SHARE

Archive

Search Archive


 
 

Discovery: Atlantic Education & the Law – issue 04

June 12, 2019

We are pleased to present the fourth issue of Discovery, our very own legal publication targeted to educational institutions in Atlantic Canada. While springtime for universities and colleges signal the culmination of classes, new graduates…

Read More

How employers can protect themselves with respect to social media

May 29, 2019

Grant Machum and Richard Jordan   In an earlier article, we considered an employer’s options when an employee departs and takes with them the social media contacts they have obtained during the course of their…

Read More

Canada’s Digital Charter – a principled foundation for a digital future?

May 28, 2019

Matthew Jacobs and Daniel Roth (summer student)   “… we cannot be a Blockbuster government serving a Netflix society.” – The Hon. Minister Navdeep Bains paraphrasing the Hon. Scott Brison (May 2019, at the Empire…

Read More

New reporting requirements for beneficial ownership of federal corporations coming this June

May 24, 2019

Tauna Staniland, Andrea Shakespeare, Kimberly Bungay and Alycia Novacefski The federal government has introduced new record keeping requirements for private, federally formed corporations governed by the Canada Business Corporations Act (“CBCA”). The amendments to the…

Read More

Doctors must provide ‘effective referrals’ for medical services they oppose on religious grounds: Christian Medical and Dental Society of Canada v. College of Physicians and Surgeons of Ontario, 2019 ONCA 393

May 17, 2019

Health Group, Christopher Goodridge and Matthew Jacobs The Ontario Court of Appeal confirmed in a decision released on May 15, 2019 that doctors must provide an ‘effective referral’ where they are unwilling to provide care on…

Read More

The road forward: Nova Scotia government announces and seeks input on further regulatory changes regarding funding of defined benefit pension plans

May 14, 2019

Level Chan and Dante Manna The Province of Nova Scotia is soliciting stakeholder input on significant regulatory changes to the Pension Benefits Act (“PBA”) and Pension Benefits Regulations (“PBR”).  The solicitation is accompanied by a…

Read More

Changes to Canadian cannabis licensing application process

May 9, 2019

Kevin Landry Health Canada has announced changes to the cannabis licensing regime. These changes come ahead of the release of the cannabis edibles, extracts, and topicals amendments to the Cannabis Regulations expected to be released…

Read More

Managing change in the workplace – constructive dismissal and the duty to mitigate

May 3, 2019

Grant Machum Last week’s Nova Scotia Court of Appeal’s decision in Halifax Herald Limited v. Clarke, 2019 NSCA 31, is good news for employers. The Court overturned the trial judge’s determinations that an employee had…

Read More

New Trade Union Act General Regulations addresses (in part) *snapshot* approach to construction industry unionization

May 2, 2019

Rick Dunlop On April 24, 2019, the Nova Scotia Government created the Trade Union Act General Regulations so that the Labour Board will no longer consider a Saturday, Sunday, or holiday as the date of…

Read More

Caution – Reform ahead for Newfoundland and Labrador automobile insurance

April 18, 2019

Rodney Zdebiak and Anthony Granville On Monday, April 15, 2019, the Newfoundland and Labrador legislature passed a number of changes to the Automobile Insurance Act (“Act”) stating that the intent is to help stabilize insurance rates,…

Read More

Search Archive


Scroll To Top