Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Federal Government announces significant investments in Nova Scotian clean energy initiatives

July 21, 2022

Nancy Rubin & Tiegan Scott On July 21, 2022, the Federal government announced a new investment of up to $255 million for clean energy initiatives in Nova Scotia. The funds will be allocated in two…

Read More

The winds of change (part 2): Crown Land

July 21, 2022

By: John Samms, Sadira Jan, Paul Kiley, Dave Randell, Alanna Waberski,  and Jayna Green Now that the Government of Newfoundland and Labrador (“GNL”) has amended the Order in Council that had banned Crown titles and…

Read More

Significant Amendments to the Business Corporations Act (New Brunswick) Proposed

July 20, 2022

By Paul Smith, Dave Randell and Graham Haynes On June 9, 2022, the Government of New Brunswick (“GNB”) released a consultation paper entitled Proposal to Modernize the Business Corporations Act (the “Proposal”) which outlines several significant…

Read More

Keep your hands off my records: solicitor-client privilege & access to information

July 19, 2022

Included in Discovery: Atlantic Education & the Law – Issue 10 Koren Thomson & Josh Merrigan   Introduction In the wake of the Supreme Court of Canada’s decision in Alberta (Information and Privacy Commissioner) v…

Read More

Beyond the border: Immigration update – July 2022

July 18, 2022

We are pleased to present the ninth installment of Beyond the Border, a publication for employers aiming to provide the latest information and analysis on new immigration programs and immigration-related issues. In this issue, insight…

Read More

A long – but not inordinate – delay may give rise to serious concern, but is not an abuse of process: Law Society of Saskatchewan v Abrametz, 2022 SCC 29

July 14, 2022

Kathleen Nash The Supreme Court of Canada’s recent decision in Law Society of Saskatchewan v Abrametz clarifies the standard of review applicable to questions of procedural fairness and abuse of process, as it relates to…

Read More

Bornfreund v. Mount Allison University: a call for a more balanced approach to disputes under access to information legislation

July 14, 2022

Included in Discovery: Atlantic Education & the Law – Issue 10 Mark Heighton & Chad Sullivan   Overview In Marcus Bornfreund v. Mount Allison University, 2022 NBQB 50 the New Brunswick Court of Queen’s Bench…

Read More

Does academic freedom protect professors who spread COVID-19 misinformation on social media?

July 12, 2022

Included in Discovery: Atlantic Education & the Law – Issue 10 Richard Jordan & Jennifer Taylor    As the COVID-19 pandemic surges on, so does the flow of misinformation online. Academia has not been immune,…

Read More

Update: The winds of change (part 1) – Newfoundland and Labrador Government signaling major shift in energy policy

July 6, 2022

John Samms and Matthew Craig Further to our original article published on May 17, 2022 (included below), on the changing energy policy frameworks in Newfoundland and Labrador, the government amended the Order in Council (“OC”)…

Read More

Nova Scotia municipality plans changes to wind turbine regulations

June 27, 2022

By Nancy Rubin & Colton Smith    Wind turbine regulations in the Municipality of Cumberland are set to change.   On June 22, 2022, Cumberland Council approved a second reading of amendments relating to their…

Read More

Search Archive


Scroll To Top