Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Client Update: It’s here now! Breach reporting for Canadian businesses under PIPEDA

October 19, 2018

Rob Aske You likely heard rumblings over the spring and summer, but now it’s here. Canada’s federal privacy law known by the acronym PIPEDA (Personal Information Protection and Electronic Documents Act) adds privacy breach reporting…

Read More

Client Update: Recent Proposed Leaves for Nova Scotia

September 28, 2018

Guy-Etienne Richard The Nova Scotia government introduced Bill 29 on September 14, 2018 to increase pregnancy and parental leave to reflect the recent changes by the federal government to Employment Insurance (“EI”). Those EI changes…

Read More

Discovery: Atlantic Education & the Law – issue 03

September 26, 2018

We are pleased to present the third issue of Discovery: Atlantic Education and the Law, our very own legal publication targeted to educational institutions in Atlantic Canada. A new school year has begun and fall…

Read More

Client Update: Border concerns growing for cannabis industry participants

July 27, 2018

Kevin Landry News articles have reported Canadians being labelled as “inadmissible” or being denied entry at the United States’ border because of ties to the cannabis industry. Being labeled inadmissible by border authorities is the…

Read More

Client Update: Duty to consult in Prince Edward Island (Epekwitk)

June 29, 2018

Jonathan Coady and Justin Milne On June 25, 2018, the Supreme Court of Prince Edward Island (the “Supreme Court”) released its much anticipated decision in Mi’kmaq of P.E.I. v. Province of P.E.I.2 This is the first…

Read More

Client Update: Cannabis Act Regulations Revealed

June 28, 2018

Kevin Landry Health Canada released the Cannabis Act Regulations (the “Regulations”) at a news conference on June 27, 2018. The Regulations will be published in final form in the July 11, 2018 version of in…

Read More

Client Update: Keeping up with crypto – CSA issues another staff notice; AML regulations proposed to be amended

June 26, 2018

Andrew Burke, David Randell and Divya Subramanian There is never a dull moment when it comes to cryptocurrency: whether it is the hacking of a South Korean crypto exchange, the U.S. Securities and Exchange Commission…

Read More

Client Update: Isn’t Canada Day always on July 1? (updated)

June 21, 2018

Grant Machum and Sheila Mecking While most people think Canada Day is on July 1st, once every 6 years, July 1st falls on a Sunday. When that happens, according to federal legislation, Canada Day is…

Read More

Client Update: Introduction of Prince Edward Island’s new Business Corporations Act

June 14, 2018

James Travers, QC and Justin Milne A new Bill, the Business Corporations Act (“Act”), recently passed by the Prince Edward Island legislature, has made significant changes to the way corporations will be governed in Prince…

Read More

Client Update: Bylaw requirements under the Municipal Government Act

June 7, 2018

Perlene Morrison and Hilary Newman Municipalities in Prince Edward Island entered a new era when the Municipal Government Act (the “MGA”) was proclaimed into force on December 23, 2017. The MGA modernized the Province’s municipal…

Read More

Search Archive


Scroll To Top